Environmental Assessment Completed

Dry Fork Flume Trailhead Relocation 2012

Ashley National Forest Uintah, Utah Vernal Ranger District

A DN/FONSI on the Dry Fork Flume Trailhead was signed in August 2011. Due to private in-holding access issues, a new location for the trailhead further up canyon has now been identified which would better facilitate all-around winter use.

Location

The new trailhead location would be 1.6 miles further up canyon at the intersections of Forest Roads 018 and 031.

Project timeline

1
Scoping Start
08/01/2012
2
Comment Period
08/01/2012
3
Decision
02/2013 (Estimated)
4
Implementation
04/2013 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Plan Amendment
Flume Trailhead Relocation ProjectDecision Signed Date: 02/22/2013 Legal Notice Date: 02/27/2013
ForestsAshley National Forest
DistrictsVernal Ranger District
Legal Land DescriptionT2S R19E, Sec. 26, SLM