Decision Memo Completed

Cliff Lake Dam Repair Project

Ashley National Forest Uintah, Utah Ashley National Forest All Units

Reissuance of a 10 year Special Use Permit to the Ouray Park Irrigation Company allowing them to impound water in the Cliff Lake Reservoir for agricultural use as well as repair the dam at Cliff Creek Reservoir

Location

Cliff Lake Reservoir

Project timeline

1
Scoping Start
06/10/2014
2
Decision
08/2014 (Estimated)
3
Implementation
09/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Cliff Lake Dam Repair Project Decision MemoDecision Signed Date: 08/11/2014
ForestsAshley National Forest
DistrictsVernal Ranger District
Legal Land DescriptionSalt Lake Meridian, T1S,R17E, Section 22
Special use managementWatershed management