Renewal of a communication use lease and the construction of a new generator building within the established limits of the State of Utah/Division of Information Technologys authorized area, located at the Grizzly Ridge Communication Site.
Location
Grizzly Ridge Communication Site
Project timeline
1
Scoping Start
05/24/2012
2
Comment Period
05/30/2012
3
Decision
09/2012 (Estimated)
4
Implementation
10/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| State of Utah at Grizzly Ridge Comm Site | Decision Signed Date: 09/19/2012 Legal Notice Date: 09/26/2012 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | NW1/4NW1/4NW1/4, sec. 17, T. 1 S., R. 22 E., SLM. Uintah County, Utah |