The proposal includes clearing and hardening a parking area ½ acre in size to accommodate vehicle and trailer traffic and constructing/installing a restroom facility, barriers, benches, gate, and a kiosk/information board and appropriat signing.
Location
The proposed trailhead location has historically been used as a dispersed camping area and is adkacemt tp tje F;i,e Trao; approx 1/4 mi. N. of Forest boundary
Project timeline
1
Scoping Start
05/17/2010
2
Comment Period
08/31/2011
3
Decision
08/2011 (Estimated)
4
Implementation
08/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Plan Amendment; Trail Management |
| Flume Trailhead Development Project | Decision Signed Date: 08/24/2011 Legal Notice Date: 08/31/2011 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | SLM, T. 2 S., R. 19 E., Sec. 36, SE ¼; 40º35'55" N, 109º43'56" W, NAD83 |