This project would replace an existing communications shelter that currently does not meet design standards. The proposed new shelter would provide a safer environment for the electronic equipment.
Location
This project is located at the Dry Ridge Repeater Site.
Project timeline
1
Scoping Start
04/25/2024
2
Decision
05/2024 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Dry Ridge Communications Shelter Replacement | Decision Signed Date: 05/29/2024 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |