Amendment of an existing special use authorization for Flaming Gorge Corp to build a 36-slip transient boater docking facility and attenuator at Lucerne Valley Marina.
Location
Lucerne Valley Marina, Flaming Gorge Reservoir
Project timeline
1
Scoping Start
10/18/2018
2
Decision
02/2019 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lucerne Marina Dock (Special Use Permit) | Decision Signed Date: 02/14/2019 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |