Decision Memo Completed

T-Mobile Cellular Communications Project

Ashley National Forest Utah, Utah Ashley National Forest All Units

T-Mobile would install a new 11' x 20' communications shelter adjacent to Strata Networks' recently constructed cell tower. T-Mobile would co-locate signal receiver dishes on the Strata Networks tower.

Location

Grizzly Ridge communications site. 22 miles north of Vernal Utah, ? mile west of 191.

Project timeline

1
Scoping Start
04/30/2021
2
Decision
06/2021 (Estimated)
3
Implementation
06/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
T-Mobile Cellular Communications ProjectDecision Signed Date: 06/14/2021
ForestsAshley National Forest
DistrictsVernal Ranger District
Legal Land DescriptionNot Applicable
Special use management