Meteorological station on an existing FS Communications tower, located at the Dry Ridge Comm site.
Location
Dry Ridge Communication site
Project timeline
1
Scoping Start
04/06/2012
2
Comment Period
04/11/2012
3
Decision
07/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Weather Station At Dry Ridge Comm. Site | Decision Signed Date: 07/26/2012 Legal Notice Date: 08/08/2012 |
| Forests | Ashley National Forest |