Long-term authorization for the Wyoming Game and Fish Commission to continue to use the facilities at the Alkali feedground on National Forest System land to conduct winter elk feeding and related management programs.
Location
Approximately 13 miles east of Kelly, Wyoming; south of the Gros Ventre River
Project timeline
1
NOI in Federal Register
04/23/2012
2
DEIS NOA in Federal Register
04/19/2013
3
FEIS NOA in Federal Register
01/23/2015
4
Objection Period Start
01/29/2015
5
Decision
12/2015 (Estimated)
6
Implementation
12/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Long Term Special Use Authorization for the Wyoming Game & Fish Commission | Decision Signed Date: 12/01/2015 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |