Construction of communication site building and tower, in addition to existing tower at White Pine Communication Site.
Location
White Pine Communication Site, Fortification Mountain, east side of Forest Road 740 (Skyline Drive).
Project timeline
1
Scoping Start
03/15/2013
2
Comment Period
03/15/2013
3
Decision
03/2014 (Estimated)
4
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| White Pine Communication Site Building and Tower Construction Project | Decision Signed Date: 03/13/2014 |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | T35N R108W Section 28 SE 1/4 |