Construction, operation & maintenance of a water transmission pipeline to supply water to 2 residences which. The ROW would be 3661' x 10'. It would be located 10' to the west of the road and be buried 7' below the existing grade of the road.
Location
Bryan Flat Rd./McKoy Rd. in the Bryan Flat area
Project timeline
1
Scoping Start
01/03/2014
2
Comment Period
01/06/2014
3
Decision
02/2014 (Estimated)
4
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Authorization of a water transmission line - Bryan Flat Rd./McKoy Rd. area | Decision Signed Date: 02/14/2014 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | T38N, R115W, section 9 |