Reauthorization of a sewer transmission line across NFS lands for Teton Village Water and Sewer District. This ROW encompasses approximately 340 ft. x 25 ft. This use has been authorized since 1994.
Location
Within the permit area of the Jackson Hole Mountain Resort at the bottom of the ski hill adjacent to the Four Seasons property
Project timeline
1
Scoping Start
10/22/2014
2
Decision
11/2014 (Estimated)
3
Implementation
01/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| ton Village Water & Sewer District Sewage Transmission Line Reauthorization | Decision Signed Date: 11/25/2014 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | SW ¼ NE ¼ Section 24, T42N, R117W |