Decision Memo Completed

Water Transmission Line Authorization - Awve

Bridger-Teton National Forest Teton, Wyoming Jackson Ranger District

Reauthorization of a 2" water transmission pipeline and headbox to convey irrigation and stock water from Barrell Spring to private property.

Location

Approximately 9 miles south of Jackson, WY, just north of Ross Plateau.

Project timeline

1
Scoping Start
01/14/2015
2
Decision
02/2015 (Estimated)
3
Implementation
02/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Water Transmission Line Authorization - AwveDecision Signed Date: 02/17/2015
ForestsBridger-Teton National Forest
DistrictsJackson Ranger District
Legal Land DescriptionNW 1/4 Section 11, T39N, R116W
Special use management