Installation of a 775 ft. long single phase electric underground primary distribution line within a conduit and transformer in order to service a permitted well on NFS lands. Due to a WYDOT project, the existing powerline and poles must be removed.
Location
Between Horsethief canyon and Game Creek adjacent to Highway 26/89/191.
Project timeline
1
Scoping Start
02/07/2017
2
Decision
04/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lower Valley Energy Powerline Burial | Decision Signed Date: 04/04/2017 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | T. 40 N., R. 116 W. sec. 27, SW1/4 |