Reauthorization with no change of a spring and 2" diameter water transmission line 250 ft. in length and collection box for domestic use.
Location
Approximately 5 miles south of Jackson, WY; near the intersection of Henry's Rd. and Highway 89.
Project timeline
1
Scoping Start
05/03/2017
2
Decision
07/2017 (Estimated)
3
Implementation
07/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Water Transmission Line Authorization -- Bauknight | Decision Signed Date: 07/18/2017 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |