Decision Memo Completed

Esther Pump Station Permit Modification

Bridger-Teton National Forest Teton, Wyoming Jackson Ranger District

Replacement of the Teton Village Water and Sewer District's 50 year-old Esther Pump Station.

Location

Near Esther Way in Teton Village, Wyoming

Project timeline

1
Scoping Start
11/30/2017
2
Decision
12/2017 (Estimated)
3
Implementation
01/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Pump House Replacement Project -- Teton Village Water and Sewer DistrictDecision Signed Date: 12/13/2017
ForestsBridger-Teton National Forest
DistrictsJackson Ranger District
Legal Land DescriptionNot Applicable
Special use management