Silver Lake Irrigation District proposes to use a tracked drill rig and a tracked excavator to perform geotechnical tests on the dam and borrow sites to determine potential actions and complete short-term repairs.
Location
East of Pinedale inside the Bridger Wilderness Area
Project timeline
1
Scoping Start
03/15/2020
2
Comment Period
04/15/2020
3
Objection Period Start
07/11/2020
4
Decision
09/2020 (Estimated)
5
Implementation
09/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Silver Lake Dam Geotechnical Survey | Decision Signed Date: 09/01/2020 |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | T.32.N R.5.W 6th PM |