Environmental Assessment Completed

Silver Lake Dam Geotechnical Survey

Bridger-Teton National Forest Sublette, Wyoming Pinedale Ranger District

Silver Lake Irrigation District proposes to use a tracked drill rig and a tracked excavator to perform geotechnical tests on the dam and borrow sites to determine potential actions and complete short-term repairs.

Location

East of Pinedale inside the Bridger Wilderness Area

Project timeline

1
Scoping Start
03/15/2020
2
Comment Period
04/15/2020
3
Objection Period Start
07/11/2020
4
Decision
09/2020 (Estimated)
5
Implementation
09/2020 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Silver Lake Dam Geotechnical SurveyDecision Signed Date: 09/01/2020
ForestsBridger-Teton National Forest
DistrictsPinedale Ranger District
Legal Land DescriptionT.32.N R.5.W 6th PM
Special use management