Remove existing overhead power poles and install electric underground distribution lines in 3 areas on Blackrock Ranger District.
Location
Buffalo Fork River, Buffalo Fork River to Turpin and Turpin to Togwotee Pass.
Project timeline
1
Scoping Start
03/26/2020
2
Decision
08/2020 (Estimated)
3
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lower Valley Energy Powerline Burial: Buffalo Valley to Togwotee Mountain L | Decision Signed Date: 08/17/2020 |
| Forests | Bridger-Teton National Forest |
| Districts | Buffalo Ranger District |
| Legal Land Description | Not Applicable |