Project timeline

1
Scoping Start
04/08/2022
2
Decision
07/2022 (Estimated)
3
Implementation
09/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Riverbend McNeel Phase II River ImprovementsDecision Signed Date: 07/12/2022
ForestsBridger-Teton National Forest
DistrictsBig Piney Ranger District
Legal Land Description37N113W Sec 23,26,35
Climate change adaptationWatershed management