JHMR proposes to increase skier/staff safety and grooming efficacy by recontouring 18 acres of ski runs. The proposed action includes blasting, grading, tree removal, road construction, and snowmaking pipeline installation. Scoping ended 1/31/23.
Location
Located within the special use permit boundary at Jackson Hole Mountain Resort near the north of the Thunder lift unload terminal and east of the Sublette lift load terminal.
Project timeline
1
Scoping Start
01/17/2023
2
Decision
03/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Jackson Hole Mountain Resort Ski Run 2023 Improvements | Decision Signed Date: 03/23/2023 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | T42N R117W Sec 14, 23, 6th Principal Meridian |