A-OK Corral proposes to move its guided horseback ride operation from Horse Creek to the North Fork of Fall Creek area. A-OK would operate within the existing base camp and existing permit area. Several improvements are proposed. Comment by 5/5/23.
Location
T39N, R117W, Sec.5, NE1/4
Project timeline
1
Scoping Start
04/20/2023
2
Decision
06/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (20), 36 Cfr 220.6(E)(20); 32.12 (12), 36 Cfr 220.6(D)(12); 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Special Use Authorizations; Trail Management; Watershed Improvements |
| Fall Creek A-OK Corral Permit Relocation | Decision Signed Date: 06/15/2023 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |