Decision Memo Completed

Kendall Gravel Pit

Bridger-Teton National Forest Sublette, Wyoming Pinedale Ranger District

Temporary Forest gravel pit (7 ac) would be developed to provide material for resurfacing the Union Pass and Green River Lakes Rds, then reclaimed. Material would be crushed & gravel stockpiled at Kendall Guard Station by contract or county agreement

Location

Behind the Kendall Guard Station in the Upper Green River area.

Project timeline

1
Scoping Start
06/28/2023
2
Decision
07/2023 (Estimated)
3
Implementation
09/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations; Road Maintenance
Kendall Gravel PitDecision Signed Date: 07/27/2023
ForestsBridger-Teton National Forest
DistrictsPinedale Ranger District
Legal Land DescriptionSW  of Section 14, T.38.N, R.110.W, 6th PM
Special use managementRoad managementMinerals and geology