Jackson Fork Ranch proposes to bring power, fiber optic, & natural gas from US Highway 189/191 along Upper Hoback Road (CR 23-174) to their property boundary, about 11,000 feet of NFS land. Project would remove 50 power poles and cross 15 culverts.
Location
Along Upper Hoback River Road (CR 23-174), Bondurant, WY
Project timeline
1
Scoping Start
06/03/2024
2
Decision
07/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Jackson Fork Ranch Utilities | Decision Signed Date: 07/16/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Big Piney Ranger District |
| Legal Land Description | Not Applicable |