JHMR proposes to connect water and sewer lines to existing on mountain facilities, construct a patrol station at the top of the Tram, and add snowmaking infrastructure to the Teewinot Switchback and Rendezvous Trail. Scoping comments by 4/1.
Location
The project area is within the special use permit boundary of Jackson Hole Mountain Resort, adjacent to Teton Village, WY.
Project timeline
1
Scoping Start
03/03/2025
2
Decision
04/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Jackson Hole Mountain Resort 2025 Mountain Improvements | Decision Signed Date: 04/22/2025 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |