Idaho Power and Rocky Mountain Power propose to construct electric transmission lines from the proposed Windstar Substation near the Dave Johnston Power Plant at Glenrock, WY to the proposed Hemingway substation near Melba, Idaho
Location
Montpelier District, CTNF - northern most corridor designated in the Caribou NF Plan, Doulgas Distict MBRNF northern most corridor designated in the MBR Plan.
Project timeline
1
NOI in Federal Register
05/16/2008
2
DEIS NOA in Federal Register
07/29/2011
3
FEIS NOA in Federal Register
04/26/2013
4
Decision
09/2013 (Estimated)
5
Implementation
11/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Gateway West 230/345/500-kV Transmission Line Project Record of Decision | Decision Signed Date: 09/18/2013 Legal Notice Date: 09/26/2013 |
| Gateway West 230/345/500-kV Transmission Line Project | Decision Signed Date: 09/23/2013 Legal Notice Date: 09/26/2013 |
| Forests | Medicine Bow-Routt National Forest; Caribou-Targhee National Forest |
| Districts | Douglas and Thunder Basin Ranger District; Montpelier Ranger District |
| Legal Land Description | Not Applicable |