Renewal of their existing electrical transmission line special use permit that includes replacing exciting poles, routine maintenance on the existing utility access road and corridor clearing to 50-feet each side of centerline.
Location
Located along I-15 beginning 8 mi. south of Monida Pass and ending 2 mi. north of Spencer, Idaho
Project timeline
1
Scoping Start
10/15/2014
2
Decision
05/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Idaho Power SUP Reissuance | Decision Signed Date: 05/23/2016 |
| Forests | Caribou-Targhee National Forest |
| Districts | Dubois Ranger District |
| Legal Land Description | Not Applicable |