Fall River Electric will install a buried powerline to supply electricity to private land from an existing powerline.
Location
From a junction box along the Railroad Trail 001 to the intersection of Forest Road #333 to the intersection of Forest Road #188 to the private land.
Project timeline
1
Scoping Start
10/24/2014
2
Comment Period
01/12/2015
3
Objection Period Start
04/08/2015
4
Decision
06/2015 (Estimated)
5
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Fall River Electric Special Use Permit | Decision Signed Date: 06/11/2015 |
| Forests | Caribou-Targhee National Forest |
| Districts | Ashton/Island Park |
| Legal Land Description | T.13N., R.43E., Section 24 |