Environmental Assessment Completed

Toms Creek Powerline

Caribou-Targhee National Forest Fremont, Idaho Ashton/Island Park

Fall River Electric will install a buried powerline to supply electricity to private land from an existing powerline.

Location

From a junction box along the Railroad Trail 001 to the intersection of Forest Road #333 to the intersection of Forest Road #188 to the private land.

Project timeline

1
Scoping Start
10/24/2014
2
Comment Period
01/12/2015
3
Objection Period Start
04/08/2015
4
Decision
06/2015 (Estimated)
5
Implementation
07/2015 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Fall River Electric Special Use PermitDecision Signed Date: 06/11/2015
ForestsCaribou-Targhee National Forest
DistrictsAshton/Island Park
Legal Land DescriptionT.13N., R.43E., Section 24
Special use management