Create ATV connecting link from Good Enough trailhead to Scout Mtn. trail system by widening existing motorcycle trail.
Location
Moron Canyon Motorized Trail(FST 195)
Project timeline
1
Scoping Start
05/09/2016
2
Decision
09/2017 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Mormon Canyon Trail (FST#195) Widening | Decision Signed Date: 09/21/2017 |
| Forests | Caribou-Targhee National Forest |
| Districts | Westside Ranger District |
| Legal Land Description | T9S R36E Sections 7,11,12 |