The project intends to remove a no-longer regulated or needed irrigation diversion ditch that diverts and runs parallel to Crooked Creek as well as realign a portion of Forest Service Road 178.
Location
The project area is located approximately 25 air miles west of Dubois, Idaho.
Project timeline
1
Scoping Start
03/04/2024
2
Decision
09/2024 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Road Improvements/Construction; Watershed Improvements |
| Crooked Creek Restoration | Decision Signed Date: 09/10/2024 |
| Forests | Caribou-Targhee National Forest |
| Districts | Dubois Ranger District |
| Legal Land Description | Township 11 North, Range 32 East, Section 17, 20, and 21 |