The project area contains ponderosa pine and mixed conifer stands that are infected with dwarf mistletoe. The removal of approximately 331 trees infected with mistletoe will help promote a healthier regeneration of the understory.
Location
Ahlstrom Hollow
Project timeline
1
Scoping Start
04/26/2018
2
Decision
05/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Ahlstrom Sanitation Project | Decision Signed Date: 05/24/2018 |
| Forests | Dixie National Forest |
| Districts | Powell Ranger District |
| Legal Land Description | Not Applicable |