The purpose of this project is to improve wildlife habitat by increasing livestock distribution on the Coyote Hollow allotment. There is a need to add & bury eight miles of water pipeline and a solar pump through the Pacer and Antimony Creek pastures
Location
Coyote Hollow Allotment, Pacer and Antimony Creek Pastures
Project timeline
1
Scoping Start
12/05/2019
2
Decision
03/2021 (Estimated)
3
Implementation
03/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Grazing Structural Improvements |
| Coyote Hollow Pockets Pipeline | Decision Signed Date: 03/17/2021 |
| Forests | Dixie National Forest |
| Districts | Escalante Ranger District |