Decision Memo Completed

Outfitter/Guide Permit Re-issuance (Fall 2020)

Dixie National Forest Garfield; Iron; Kane; Washington, Utah Dixie National Forest All Units

Outfitter/Guide Special Use Permit Re-issuance

Location

Guides would operate throughout the Dixie National Forest where permitted.

Project timeline

1
Scoping Start
08/04/2020
2
Decision
08/2020 (Estimated)
3
Implementation
09/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Outfitter/Guide Permit Re-issuance (Fall 2020)Decision Signed Date: 08/18/2020
ForestsDixie National Forest
DistrictsDixie National Forest All Units
Legal Land DescriptionNot Applicable
Special use management