Decision Memo Completed

South Central Communications Panguitch Lake South Project

Dixie National Forest Garfield, Utah Cedar City Ranger District

Placement of a fiber optic line on the south side of Panguitch Lake. Line will be trenched in below ground.

Location

South of Panguitch Lake, UT

Project timeline

1
Scoping Start
03/30/2020
2
Decision
08/2021 (Estimated)
3
Implementation
08/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
South Central Communications Panguitch Lake South ProjectDecision Signed Date: 08/30/2021
ForestsDixie National Forest
DistrictsCedar City Ranger District
Legal Land DescriptionNot Applicable
Special use management