Approval to re-locate and drill the Boulder Farmstead culinary well 45 feet away from existing location due to the silting in of the original well.
Location
Boulder Town, Utah
Project timeline
1
Scoping Start
04/26/2021
2
Decision
05/2021 (Estimated)
3
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Dixie National Forest |
| Districts | Escalante Ranger District |
| Legal Land Description | S23 T33S R4E |