Treat vegetation to improve stand structure and diversity, improve spruce resilience to insect and disease,improve aspen regeneration, and provide a wood fiber product for public use.
Location
West of Fish Lake near Na-Gah Flat on Fishlake High-Top
Project timeline
1
Scoping Start
04/06/2011
2
Comment Period
04/09/2014
3
Objection Period Start
04/22/2015
4
Decision
06/2015 (Estimated)
5
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Teeple Springs Vegetation Management Project | Decision Signed Date: 06/15/2015 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R1E sections 2, 11-15, 22-23 |