Categorical Exclusion · Beaver Ranger District · updated 12/9/2025
Bullion Canyon Road west of Marysvale · Piute, Utah
The proposed action includes activities designed to stabilize areas along Bullion Canyon Road effected by the 2024 Silver King wildfire. These measures include flood mitigation measures to protect the town of Marysvale.
Watershed management
NEPA Start Date
6/30/2025
Finding/Decision Date
12/3/2025
NEPA / regulatory detail
| Categorical Exclusion | USDA-01d-FSA |
| Decision Signed Date | 12/3/2025 |
Environmental Assessment · Fremont River Ranger District · updated 10/27/2025
The project emcompasses approximately 210,000 acres on Boulder Mountain (old Teasdale District of the Dixie National Forest) · Garfield; Wayne, Utah
The Fremont River Ranger District is proposing vegetation and habitat improvement projects to improve landscape health and resiliency to support wildlife, aquatic, and watershed resources.
Wildlife, fish, rare plantsVegetation management (other than forest products)Fuels managementWatershed management
Comment Period
04/2025 (Estimated)
Objection Period Start
08/2025 (Estimated)
Decision
10/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fishlake National Forest All Units · updated 9/11/2025
Beaver, Fillmore, Fremont River and Richfield Ranger Districts of the Fishlake National Forest · Beaver; Millard; Piute; Sanpete; Sevier; Wayne, Utah
The purpose of this proposal is to reintroduce fire to fire-adapted ecosystems within the forest. There is a need to take action to improve the health and resiliency of vegetation communities and wildlife habitats and increase public safety.
Wildlife, fish, rare plantsVegetation management (other than forest products)Fuels managementWatershed management
Comment Period
08/2025 (Estimated)
Objection Period Start
01/2026 (Estimated)
Decision
03/2026 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 11/6/2024
East side of the Old Woman Plateau and Pine Hollow area. · Sevier, Utah
The Richfield and Fremont River Districts propose conducting prescribed fire operations within Ponderosa Pine and Aspen stands in the East Old Woman Plateau and Pine Hollow areas.
Vegetation management (other than forest products)Fuels management
Decision
11/2024 (Estimated)
Implementation
01/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District; Richfield Ranger District |
| Legal Land Description | T.21S.R.4E.Sec 36; T.22S.R.4E.Sec 1-3,10-15,22-27,34-36;T.22S.R.4E.Sec 1-3,10-15,22-27,34-36;T.22S.R.5E.Sec 5-8,17-20,29-32;T.23S.R.4E.Sec 1-3,10,11,25,26,35;T.24S.R.4E.Sec 2,3,9-16,21-26. |
Decision Memo · Fillmore Ranger District · updated 10/22/2024
The project area is approximately 5-7 miles northeast of Oak City, Millard County, Utah. · Millard, Utah
The Fillmore Ranger District is working with the Utah Division of Wildlife Resources to improve winter forage for Mule Deer by planting and seeding various native shrubs on approximately 180 acres of NFS land near Oak Creek Canyon.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 10/2/2024
Approximately 3 miles north of Cove Fort and east of I-15 in the Dog Valley area. · Millard, Utah
Zanskar proposes to use passive seismic survey equipment to gather baseline data on potential geothermal lease parcels near Cove Fort, UT.
Minerals and geology
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Geothermal |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T24S R6W Sections 17 and 20; T25S R6W Sections 5, 8, 17, 20, 21, 28, 29 |
Decision Memo · Fremont River Ranger District · updated 9/20/2024
Approximately 2.7 miles southwest of Mount Terril Guard Station within the Seven-Mile area. · Sevier, Utah
The Fremont River Ranger District proposes to realign less than one mile of road and rehabilitation the closed portion of the road. The project is needed to address ongoing erosion and improve safety.
Road management
Decision
09/2024 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T24S R2E Sections 20, 21, 28, and 29 |
Decision Memo · Fremont River Ranger District · updated 9/10/2024
Approximately 0.75 miles northwest of Spectacle Lake, between the Aquarius Plateau and Boulder Mountain · Garfield, Utah
The Fremont River Ranger District is proposing to authorize a special use permit for the NRCS to install of a SNOTEL monitoring site on Boulder Mountain.
Special use management
Decision
09/2024 (Estimated)
Implementation
09/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T31S R3E Sec 25 |
Decision Memo · Fishlake National Forest All Units · updated 8/27/2024
Upper Deer Mountain Trail- US-89 to to Deer Trail Mine/Cottonwood Canyon Road then take FS 125. Horse Heaven Pad will be located at the intersection of FS 1112 and FS 1113. · Piute, Utah
DT Mining proposes to upgrade 0.6 miles of road and construct one drill pad in support of mineral exploration activities on their mining claims southwest of Marysvale Utah
Minerals and geology
Decision
08/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations; Road Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T28S, R4W, Sec 2,9 Salt Lake Meridian |
Decision Memo · Fishlake National Forest All Units · updated 6/26/2024
One near Robins Valley and the other east of Geyser Peak on Thousand Lakes Mountain. · Sevier, Utah
The Utah Communications Authority proposes to install a new small communication site on the Fillmore Ranger District. The Bureau of Land Management proposes to install a new small communication site on the Fremont River Ranger District.
Special use management
Decision
05/2024 (Estimated)
Implementation
05/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District; Fremont River Ranger District |
| Legal Land Description | Robins Valley-Township 20 South, Range 2 West, Section 31, Sevier County Thousand Lakes-Township 26 South, Range 4 East, Section 34, Sevier County |
Environmental Assessment · Fishlake National Forest All Units · updated 6/13/2024
Fishlake National Forest · Beaver; Garfield; Iron; Juab; Millard; Piute; Sanpete; Sevier; Wayne, Utah
Fishlake NF is proposing a forest-wide prescribed fire project to reduce the risk of uncharacteristic wildfires, increase resilience of existing vegetation groups, and improve ecological function in native vegetation communities and wildlife habitats
Fuels managementWatershed managementWildlife, fish, rare plantsVegetation management (other than forest products)
Comment Period
10/20/2021
Objection Period Start
02/2022 (Estimated)
Decision
03/2022 (Estimated)
Implementation
03/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Beaver Ranger District · updated 6/11/2024
Project activities would take place near the Alunite Ridge and North Fork areas on the east side of the Tushar Mountain Range and approximately 6 miles southwest of Marysvale, Utah in Piute County. · Piute, Utah
Project ID 66361 was Cancelled because the same project (#66362) already exists on the SOPA. Those interested in information related to this project, should refer to project 66362. Project 66361 will appear on the SOPA for one quarter before removed.
Minerals and geology
Scoping Start
06/2024 (Estimated)
Comment Period
06/2024 (Estimated)
Objection Period Start
10/2024 (Estimated)
Decision
12/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T27S R4W Section 34; T28S R3W Section 18; and T28S R4W Sections 1-3, 8, 9, 11-14, 16, 17, 20, 21, 23, and 24. |
Decision Memo · Fishlake National Forest All Units · updated 4/30/2024
Fish Lake basin along Hwy 25 from Fish Lake Lodge to Bowery Haven. · Sevier, Utah
Fremont River Ranger District proposes authorizing a special use permit for the extension of a fiber optic line from Fish Lake Lodge to Bowery Haven.
Special use management
Decision
04/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Township 26 S, Range 2 E, Sections 08, 09, and 17 |
Decision Memo · Beaver Ranger District · updated 4/22/2024
Fish Creek and Shingle Creek area. South of the Clear Creek Canyon Road, within the Joe Lott / Fish Creek Allotment on the Beaver Ranger District of the Fishlake National Forest. · Sevier, Utah
The Beaver Ranger District proposes to make range improvements for the purpose of improved livestock distribution.
Grazing management
Decision
04/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fillmore Ranger District · updated 3/26/2024
The Flat Canyon Allotment is west of Interstate 70, spanning from Richfield to south of Elsinore, on the Pahvant Mountain Range. · Sevier, Utah
The Fillmore Ranger District will analyze three alternatives to inform a decision of grazing management on Flat Canyon Allotment. Proposed alternatives include current management (winter sheep grazing), conversion to cattle grazing, and no grazing.
Grazing management
Comment Period
07/05/2023
Objection Period Start
12/27/2023
Decision
03/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Multiple sections within Ranges 3 and 4 West, Townships 23, 24, and 25 South. |
Decision Memo · Fishlake National Forest All Units · updated 2/6/2024
Near Oak City · Millard, Utah
T-Mobile has requested to co-locate on a currently permitted communication site near Oak City. A small expansion has been requested to make room for needed equipment.
Special use management
Decision
02/2024 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Township 17 South, Range 5 West, Section 12, Millard County |
Decision Memo · Fremont River Ranger District · updated 1/23/2024
Both campgrounds are located adjacent to Fish Lake along State Route 25. · Sevier, Utah
The Forest Service is proposing to improve two existing campgrounds at Fish Lake, Bowery Creek and Mackinaw Campgrounds.
Recreation management
Decision
01/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R2E Sections 8 and 17 |
Environmental Assessment · Beaver Ranger District · updated 12/20/2023
Sulphurdale area, near the junction of I15 and I70. Portions of T26S, R6W, Sections 3, 4, 10, 15, 21, 22, 28-33; T26S, R7W, Section 25. · Beaver; Millard, Utah
USFS federal action to decide whether to consent to the BLM three parcels for geothermal resources.
Minerals and geology
Comment Period
04/26/2023
Objection Period Start
09/27/2023
Decision
12/2023 (Estimated)
Implementation
01/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 11/7/2023
Sand Creek Trailhead approximately 1.6 miles northwest of Torrey, UT, and Beehive Peak Overlook approximately 20 miles south of Scipio, UT off Pauite ATV Trail 01. · Sevier; Wayne, Utah
The Fremont River and Fillmore Ranger Districts propose installing a single unit restroom facility at two locations receiving high traffic, Sand Creek Trailhead and Beehive Peak Overlook, to address sanitation issues and improve visitor satisfaction.
Recreation management
Decision
11/2023 (Estimated)
Implementation
09/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District; Fremont River Ranger District |
| Legal Land Description | T21S R2.5W Sec 27 and T29S R4E Sec 2 |
Decision Memo · Fillmore Ranger District · updated 10/3/2023
T21S R2.5W Section 1 · Millard, Utah
The Fillmore Ranger District proposes to install post and rail fence around Ivie Creek from the Maple Grove Campground northeast to the forest boundary, excluding Forest Road 886 and hardening the road over a stream crossing to protect stream habitat
Watershed management
Decision
10/2023 (Estimated)
Implementation
11/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 9/26/2023
The analysis area, where management activities are proposed, would take place on the Teasdale portion of the Escalante Ranger District of the Dixie National Forest (administered by the FNF) · Garfield, Utah
The Fishlake National Forest proposes the installation of a up to two fish passage barriers on Pleasant Creek Ditch to protect Colorado River cutthroat trout. The barriers will be constructed from boulders on site.
Wildlife, fish, rare plants
Decision
09/2023 (Estimated)
Implementation
09/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Dixie National Forest; Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 7/26/2023
Boulder Mountain east of Hwy 12 · Garfield; Wayne, Utah
The Fremont River Ranger District proposes to install exclosures on three springs and pipe water to three troughs and one pond to eliminate direct use at these springs by livestock which has damaged riparian vegetation and diminished water quality.
Grazing management
Decision
07/2023 (Estimated)
Implementation
08/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T30S R5E Section 35 and T32S R5E Section 11 |
Decision Memo · Beaver Ranger District · updated 6/29/2023
Near Big John's Road (FR123) and FR 1062, approximately 16 miles east of Beaver, Utah. · Beaver, Utah
Kent's Lake Ditch Company is proposing to install a measuring weir with a small solar panel on Merchant Creek near Big John's Road (FR123) and FR 1062. This will provide an accurate measurement of water flow in the drainage.
Special use management
Decision
06/2023 (Estimated)
Implementation
07/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Beaver Ranger District · updated 3/28/2023
Project location is northwest of Circleville along Cottonwood Creek and northwest of Torrey in the Sand Creek and Sulphur Basin areas. · Piute; Wayne, Utah
Circleville and Torrey Towns need to improve their culinary water supply for their residents. Cottonwood Springs will be redeveloped and a waterline replaced for Circleville. Torrey will install a new water tank and waterline.
Special use management
Decision
03/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District; Beaver Ranger District |
| Legal Land Description | T30S R4W Sections 7 and 8, Piute County; T28S R4E Sections 34 and 35 and T29S R4E Section 2, Wayne County |
Decision Memo · Beaver Ranger District · updated 3/9/2023
Near Deer Trail Mountain. Approximately 5 miles south of Marysvale, Utah. · Piute, Utah
DT Mining LLC has proposed a .9 mile extension of FS Road 1108. The extension would follow a previously decommissioned route. The project would consist of grading the entire .9 miles and widening of the road in needed locations.
Minerals and geology
Decision
03/2023 (Estimated)
Implementation
05/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations; Road Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T28S, R4W, Sections 13 & 14, Salt Lake Meridian |
Decision Memo · Fremont River Ranger District · updated 12/13/2022
The project site is on Lower Bowns ditch about 0.8 mile west of Pleasant Creek Campground and Hwy 12 and 0.1 mile north of Forest Road 168 on Boulder Mountain. · Garfield, Utah
The Fishlake National Forest proposes the installation of a new fish passage barrier on Lower Bown Ditch to protect Colorado River cutthroat trout which will be restored in Pleasant Creek. The barrier will be constructed from boulders on site.
Wildlife, fish, rare plants
Decision
12/2022 (Estimated)
Implementation
09/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T31S R5E Section 23 |
Environmental Assessment · Beaver Ranger District · updated 9/27/2022
Project activities would take place on the east side of the Tushar Mountain Range near Deer Trail Mountain between Twomile Creek and Cottonwood Creek, approximately 6 miles southwest of Marysvale, UT. · Piute, Utah
The Beaver District of the Fishlake National Forest is proposing to authorize mining exploration to DT Mining, LLC, which consists of 13 exploration drill pads (with drill depths of approx. 5,000 ft.) near Deer Trail Mountain in the Tushar Range.
Minerals and geology
Comment Period
04/20/2022
Decision
09/2022 (Estimated)
Implementation
03/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Township 28 South, Range 4 West, Sections 10, 12, and 13 |
Decision Memo · Fillmore Ranger District · updated 8/8/2022
On the Pahvant Mountain Range approximately 0.1 mile north of Forest Road 110, on a spur road to the site of the former Rockwood Ranger Station. · Sevier, Utah
The Fishlake National Forest proposes to authorize the installation of an NRCS SNOTEL site on the Fillmore Ranger District to gather automated data to improve knowledge of current and future climatological conditions for a variety of users.
Special use management
Decision
08/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Township 24 South, Range 4.5 West, Section 34 |
Decision Memo · Fremont River Ranger District · updated 6/22/2022
Fish Lake Basin at Lakeside Marina · Sevier, Utah
Fish Lake Resorts proposes to demolish their existing marina building and replace with one slightly larger (20' x 40')approximately 30 feet southeast of the existing building. A larger marina structure is needed to provide services for the marina.
Special use management
Decision
06/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R2E Section 19 |
Environmental Assessment · Fremont River Ranger District · updated 6/17/2022
Fish Lake Basin · Sevier, Utah
The Fishlake National Forest is proposing a recreation improvement project which includes boat docking stations, Pando interpretive plazas, electric bicycle (e-bike) trail designations, new trails, and fuels reduction in recreation residence tracts.
Fuels managementRecreation management
Comment Period
04/28/2021
Objection Period Start
04/06/2022
Decision
06/2022 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Fuel Treatments (Non-Activity Fuels); Facility Maintenance; Trail Management |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T25S, R2E, Sections 23, 25-27, 33-36; T26S, R1E, Sections 13, 24, and 25; T26S, R2E, Sections 1-6, 8-13, 15-21, 29, and 30; T26S, R3E, Sections 7, 8, 16-21, and 29. |
Environmental Assessment · Fillmore Ranger District · updated 5/10/2022
Dog Valley north of Cover Fort, Utah. T24N, R6W, Sec. 32 and 33; T25N, R6W, Sec. 4,5, and 8. · Millard, Utah
USFS federal action to decide whether to consent to the BLM two parcels for geothermal resources.
Minerals and geology
Comment Period
05/05/2021
Objection Period Start
02/23/2022
Decision
05/2022 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Beaver Ranger District · updated 11/24/2021
Project activities would occur approximately one mile east of Three Creeks Reservoir between Tushar Ridge and Buck Ridge. · Beaver, Utah
The Beaver Ranger District is proposing to realign a section of Forest Road 135 to enhance safe travel, improve access for forest management, improve natural resource conditions in the riparian corridor and protect historic sites in the area.
Watershed managementRoad management
Comment Period
02/10/2021
Objection Period Start
09/29/2021
Decision
11/2021 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Improvements/Construction; Watershed Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T29S R5W Sections 10,11,14, and 15 |
Environmental Assessment · Beaver Ranger District · updated 10/20/2021
Project activities would take place west of Hwy 153 at milepost 6 for the hydroelectric plant and in South Fork Baker Canyon for the spring development. · Beaver, Utah
The Fishlake National Forest is proposing authorization of an additional spring development in South Fork Baker Canyon and upgrades to a hydroelectric plant to provide reliable culinary water and electrical power for residents of Beaver City.
Special use management
Comment Period
06/02/2021
Objection Period Start
08/25/2021
Decision
10/2021 (Estimated)
Implementation
10/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T29S R6W sections 11, 14, 15, 21, and 28 |
Decision Memo · Fremont River Ranger District · updated 9/29/2021
Bowery Haven Resort within the Fish Lake Basin in Sevier County, Utah · Sevier, Utah
Bowery Haven Resort requested modifications within their permitted area: construct a larger pavilion where one was removed, replace a single-wide with a double-wide modular home for staff housing, and install a temporary, portable office building.
Special use management
Decision
09/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R2E Section 9 |
Decision Memo · Richfield Ranger District · updated 9/2/2021
The new tower will be adjacent to the existing Triangle Mountain communications site south of Interstate 70 and approximately seven miles southeast of Salina, UT. · Sevier, Utah
Fishlake National Forest proposes to authorize a special use permit to Utah Communications Authority for the installation of a new communications tower at the existing Triangle Mountain communications site to provide public safety radio coverage.
Special use management
Decision
07/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T22S R1E Section 11 |
Decision Memo · Fishlake National Forest All Units · updated 8/4/2021
Emery Telcom's fiber optic line will follow Forest Road 242 north of I-70 in Salina Canyon. Arcadian's fiber optic line will follow Hwy 89 in Sevier Canyon and Old Hwy 89 south of Elsinore, UT. · Sevier, Utah
Fishlake National Forest proposes to authorize special use permits to Arcadian Infracom and Emery Telcom for installation/maintenance of fiber optic lines to improve telecommunications services to underserved rural areas in Emery and Sevier Counties.
Special use management
Decision
08/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District; Beaver Ranger District; Richfield Ranger District |
| Legal Land Description | T26S R4W Sec. 5 - 8, 18, 19 (Beaver RD). T24S R3W Sec. 29, 31, 32; T25S R3W Sec. 6; and T 25S R4W Sec.21, 22, 29 (Fillmore RD). T23S R4E Sec. 27, 34, 35; T24S R4E Sec. 1, 2 (Richfield RD). |
Decision Memo · Fishlake National Forest All Units · updated 6/29/2021
Boulder Mountain Site: On a knoll near Sunflower Flat approx. 10 miles NE of Boulder, UT; Pahvant Range Site: on Noon Rock Peak about 4 miles south of Scipio, UT. · Garfield; Millard, Utah
The Fishlake NF proposes to authorize a Special Use permit submitted by the BLM to install and maintain two portable communications sites, one on Boulder Mountain and one on the Pahvant range, for improved fire response and other communications.
Special use management
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District; Fremont River Ranger District |
| Legal Land Description | T32S R5E Section 10 and T19S R2W Section 6 |
Decision Memo · Fremont River Ranger District · updated 6/2/2021
Along State Route 24 on the west side of Fish Lake in south-central Utah · Sevier, Utah
Rebuild the existing DWR cabin on NFS land. The proposed project consists of removing the existing cabin, building a new cabin with a deck, improving the parking lot, and installing a new water line.
Special use management
Decision
06/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Beaver Ranger District · updated 5/7/2021
Portions of the following: Sec.33 of T28S, R6W; Sec.3 of T29S. R6W; Sec.17 of T29S, R5W; Sec.2 and 3 of T29S, R4.5W; and Sec.18 of T28S., R4W. · Beaver; Piute, Utah
The purpose of this project is to improve livestock distribution and control on the North Indian, North Beaver, Ten Mile and Cottonwood Allotments.
Grazing management
Decision
05/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 11/16/2020
The targeted stands of the project area are located near Daniels Pass, Mount Marvine, and Big Flat in Sevier County. In Garfield County, the project area is in the Dark Valley and Blue Lake area. · Garfield; Sevier, Utah
The Fremont River and Richfield Ranger Districts are proposing a vegetation improvement project to create and maintain healthy and resilient spruce-fir stands by removing dead/dying Engelmann spruce, thinning live trees, planting spruce where needed.
Forest productsVegetation management (other than forest products)
Comment Period
05/07/2020
Objection Period Start
09/17/2020
Decision
11/2020 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District; Richfield Ranger District |
| Legal Land Description | T24S R1E Sec 24; T24S R2E Sec 10,11,14,15,19,20,25,27%u201336; T24S R3E Sec 25,26, 30,31; T25S R2E Sec 5,6; T26S R1E Sec 1,2,10%u201315,22,23; T31S R2E Sec 33,34; T31S R3E Sec 22,27; and T32S R2E Sec 3-5. |
Decision Memo · Fremont River Ranger District · updated 9/28/2020
NW 1/4,Section 19, T26S, R2E · Sevier, Utah
Amend Garkane Power Special Use permit to remove 2,470 feet of overhead powerline and replace with 380 feet of buried line
Special use management
Decision
01/2014 (Estimated)
Implementation
04/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Richfield Ranger District · updated 9/10/2020
These allotments are located in Sevier and Piute Counties covering multiple sections in Ranges 1, 2, 2 ½, and 3 West and Townships 26, 27, and 28 South. · Piute; Sevier, Utah
The U.S. Forest Service, Fishlake National Forest, Richfield Ranger District, is proposing to reauthorize livestock grazing on the Koosharem, Rock Springs, Dry Lake, and Hunts Lake Allotments.
Grazing management
Comment Period
12/30/2015
Objection Period Start
05/2019 (Estimated)
Decision
12/2019 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Authorizations |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 8/10/2020
The proposed project area includes areas near Big Hollow, Deer Springs, Burnt Hollow, and Mud Spring on the south end of the Pahvant Mountain Range of the Fillmore Ranger District. · Millard; Sevier, Utah
The Fillmore Ranger District proposes to implement vegetation treatments designed to thin decadent stands of sagebrush in order to rejuvenate grasses, forbs, and shrubs which will improve big game habitat and ecosystem diversity and resilience.
Grazing managementFuels managementWildlife, fish, rare plantsVegetation management (other than forest products)
Decision
08/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Rangeland Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T23S R4W Sections 3, 10, 14, 15, 22-27, 33-35; T24S R3W Sections 7, 8, 17-20, 30; T24S R4W Sections 1, 3-5, 8-16, 24-26, 34-36; T25S R4.5W Section 1; T25S R4W Sections 2, 3, 5-9, 15-17, 21, 22 |
Environmental Assessment · Fremont River Ranger District · updated 7/22/2020
The proposed project is located north of Torrey near Chaffin Springs in Wayne County, Utah. The project area is located in portions of Sections 3, 9, and 10; Township 28S; Range 4E. · Wayne, Utah
To ensure that the town of Torrey continue to supply its residences with water the Fishlake NF is proposing to develop four spring complexes with eight spring collection areas. Pipeline would then be installed to connect to existing water lines.
Special use management
Comment Period
01/23/2020
Objection Period Start
05/21/2020
Decision
07/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 5/20/2020
T26S R3E Sec35 · Wayne, Utah
The Fremont River Ranger District proposes to construct a fish passage barrier on UM Creek between Mill Meadow and Forsyth Reservoirs. The barrier built of boulders on site will protect the Colorado River cutthroat trout population in the stream.
Wildlife, fish, rare plants
Decision
05/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 1/30/2020
The Union Pacific Railroad - Oak City Communications Tower Project is located approximately 1 miles southwest of Oak City Utah, at the current telecommunications site at T17S R5W Sec.12. · Millard, Utah
Union Pacific Railroad has a current lease with the Forest Service for a communication tower. The current tower does not meet current Telecommunications Industry Association standards and a new tower with a solid leg structure needs to be built.
Special use managementFacility management
Decision
01/2020 (Estimated)
Implementation
04/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fishlake National Forest All Units · updated 12/5/2019
The project location occurs on the Beaver, Fillmore, Fremont River, and Richfield Ranger Districts of the Fishlake National Forest and the Boulder Mountain portion of the Dixie National Forest. · Beaver; Garfield; Juab; Millard; Piute; Sanpete; Sevier; Wayne, Utah
Pinyon-juniper removal on the Fishlake National Forest to improve and maintain sage-steppe, grassland, oak, and open woodland cover. Treatments include hand-cutting, mechanical and prescribed burning to address encroachment.
Vegetation management (other than forest products)
Comment Period
04/18/2019
Objection Period Start
10/03/2019
Decision
12/2019 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 11/26/2019
The fiber optic line will run from the intersection of 4690 N. and Highway 12 in Boulder and proceed north along Highway 12 to the junction of Highway 24 in Torrey in the existing road right-of-way. · Garfield; Wayne, Utah
Fishlake and Dixie National Forests propose granting a special use permit to South Central Communications (SCC) for the construction and operation a fiber optic line which would run from Boulder to Torrey to increase telecommunications services.
Special use management
Decision
11/2019 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Richfield Ranger District · updated 9/10/2019
Monroe Mountain, Richfield Ranger District · Piute; Sevier, Utah
Aspen ecosystem restoration project on Monroe Mountain to promote the regeneration and recruitment of aspen. Treatments include mechanical and prescribed burning to address conifer encroachment and thresholds/response options to address overbrowsing.
Wildlife, fish, rare plantsForest productsWatershed managementVegetation management (other than forest products)Fuels management
NOI in Federal Register
10/03/2012
DEIS NOA in Federal Register
01/16/2015
FEIS NOA in Federal Register
08/14/2015
Objection Period Start
08/19/2015
Decision
12/2015 (Estimated)
Implementation
12/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Special Products Sales; Species Population Enhancements; Rangeland Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | multiple sections in Ranges 1,2,2 1/2, and 3 West and in townships 24, 25, 26, 27, and 29 South |
Decision Memo · Fremont River Ranger District · updated 7/12/2019
The fiber line will be approx. 4.54 miles long and start at the intersection of Sleepy Ridge Ln. and CR-5429, follow Sewer Lagoon Rd. and proceed along SR-25 before attaching to the existing vault. · Sevier, Utah
The Fishlake National Forest is proposing to grant a special use permit to South Central Communications (SCC) to install, operate, and maintain a fiber optics line which will run along existing road right-of-ways in the Fish Lake basin.
Special use management
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T.26S R.2E Sec 17-19; T26S. R.1E Sec 24-27, 35-36 |
Environmental Assessment · Fremont River Ranger District · updated 7/2/2019
The majority of the project is located on the west side of Fish Lake in south-central Sevier County, Utah; one project feature occurs northeast of Johnson Valley Reservoir. · Sevier, Utah
To improve marinas facilities at Lakeside, Fish Lake Lodge, and Bowery Haven marinas, increase opportunities for shoreline fishing, and to provide increased viewing opportunities for kokanee spawning.
Recreation managementFacility management
Comment Period
04/18/2019
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 5/2/2019
Proposed activities are on the Fremont River and Richfield Ranger Districts, adjacent to Hwy 72 in the Last Chance drainage on the east side of Hilgard Mountain. · Sevier; Wayne, Utah
The Fishlake National Forest is proposing to reduce conifer encroachment into sage-grouse priority habitat by using mechanical treatments and broadcast burning, with seeding as needed. Up to six guzzlers will be installed for wildlife and game use.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
05/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | In all or portions of T24S R3-4E; T25S R4-5E; and T26S R4E. |
Environmental Assessment · Fremont River Ranger District · updated 4/18/2019
The proposed project is located along Utah State Route 25 (SR-25) at Fish Lake in south-central Sevier County, Utah. It is located in portions of Section 8, 9, 17, and 18 of Township 26S, Range 2E. · Sevier, Utah
This project has been moved to project number 55908 - Fish Lake Marinas and Recreation Improvements Project.
Recreation managementFacility management
Comment Period
03/2019 (Estimated)
Objection Period Start
04/2019 (Estimated)
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 4/18/2019
The proposed project is located along Utah State Route 25 (SR-25) at Fish Lake in south-central Sevier County, Utah. It is located in portions of Section 17, 18, 19, and 24 of Township 26S, Range 2E. · Sevier, Utah
This project has been moved to project number 55908 - Fish Lake Marinas and Recreation Improvements Project
Facility managementRecreation management
Comment Period
07/2018 (Estimated)
Objection Period Start
09/2018 (Estimated)
Decision
10/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 4/4/2019
The project area, where management activities are proposed, is on the Fremont River Ranger District just south/southwest of Hilgard Mountain, east of UM Creek and west of Tidwell Slopes. · Sevier, Utah
The Fishlake National Forest is proposing to implement prescribed fire treatments in seral aspen stands to promote the regeneration and recruitment of aspen communities. A mosaic burn pattern with a variety of fire severities is desired.
Vegetation management (other than forest products)Fuels management
Decision
04/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | In all or portions of T24S, R3E, Sections 33-35; T25S, R3, Sections 1-4, 9-16, 21-24, 26-27 and 34-35; and T26S, R3E, Sections 2-3 of the Salt Lake Base Meridian. |
Decision Memo · Fillmore Ranger District · updated 3/1/2019
The proposed trail system is located on the east side of the Pahvant Range, west of Richfield, Utah, in Sevier and Millard counties. Seven suitable trailheads would be designated along the trail. · Millard; Sevier, Utah
The Fillmore Ranger District is proposing to create a mountain bike trail system west of Richfield, Utah. The proposed 83 miles of bike trail, built to specific trail standard, will have seven trailheads and signs to inform riders of active grazing.
Recreation management
Decision
02/2019 (Estimated)
Implementation
05/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Beaver Ranger District · updated 2/12/2019
The Gold Nugget #1 and #2 Mining Claims are located approximately ten mile southwest of Marysvale, Utah, near Cottonwood Creek. · Piute, Utah
As required by regulation, the Beaver Ranger District must respond to an exploration plan of operations submitted for two mining claims. As such, the district is conducting an environmental analysis for this proposal on National Forest System lands.
Minerals and geology
Comment Period
08/30/2018
Decision
02/2019 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T28S R4W Section 20 |
Decision Memo · Richfield Ranger District · updated 11/8/2018
Near the communities of Koosharem and Greenwich. Portions of sections 28-29 and 32-33 in R.1W,T.26S; sections 5-8 and 18-19 in R.1W, T.27S; sections 1,12-23, and 24 in R.2W,T.27S. · Sevier, Utah
Improve big game wildlife habitat on the east side of Monroe Mountain by removing encroaching pinyon and juniper trees from the brush, grass, and forb areas.
Wildlife, fish, rare plants
Decision
11/2018 (Estimated)
Implementation
01/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Beaver Ranger District · updated 10/24/2018
The existing Pit is approximately three miles due west of Mount Baldy along the North Fork of North Creek. It is in the SW 1/4 of Section 1 T28S R5W SLBM · Beaver, Utah
The Beaver District Ranger is proposing to implement a pit management plan for the North Fork of North Creek Mineral Material Pit, which will define future development, production, and reclamation in order to respond to requests for permits.
Minerals and geology
Decision
10/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 10/11/2018
Wood Canyon, Pass Canyon and along the west foothills of the Canyon Range. Legal description includes portions of sec. 8, 7, and 19 of T15S R3W and portions of sec. 12, 13, 24, 25, and 36 of T15S R4W. · Millard, Utah
The Fillmore District Ranger is proposing to construct two wildlife guzzler aprons with storage ponds and pipelines to increase water availability and distribution across the north end of the Canyon Range for wildlife.
Wildlife, fish, rare plants
Decision
10/2018 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fremont River Ranger District · updated 10/10/2018
The project area is in Sevier County at elevations between 10,400-10,600 feet on Boobe Hole Mountain. · Sevier, Utah
Fishlake National Forest is proposing to do an intermediate harvest of dead Engelmann spruce (ES) in addition to timber stand improvement and planting of ES after harvest. This will provide wood fiber while maintaining or improving stand conditions.
Forest productsVegetation management (other than forest products)
Decision
10/2018 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T24S R1E Sections 24 and 25; T24S R2E Sections 19 and 30 |
Environmental Assessment · Richfield Ranger District · updated 10/4/2018
790 Acre Lease Modification in portions of: Sec. 11, T21S, R4E; Sec. 14, T21S R4E; Sec. 15, T21S R4E; Sec. 22, T21S, R4E; Sec. 23, T21S, R4E; Sec. 23, T21S, R4E. · Sevier, Utah
The BLM and U.S. Forest Service are preparing an environmental assessment to analyze the impacts of a request by Canyon Fuel Company, LLC to modify the lease boundaries for federal coal leases UTU-84102(Greens Hollow)and U-63214(Quitchupah).
Minerals and geology
Comment Period
09/07/2017
Objection Period Start
06/14/2018
Decision
10/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest; Manti-Lasal National Forest |
| Districts | Richfield Ranger District; Ferron Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fillmore Ranger District · updated 9/19/2018
Forest Road (FR)105 west of Elsinore to FR 969 in Clear Creek Canyon until it meets the boundary near Fremont Indian State Park. Chalk Creek Canyon Road (FR 100) and Oak Creek Road (FR 089). · Beaver; Millard; Sevier, Utah
Create a public OHV route that provides OHV access to area destinations by connecting existing system and non-system trails or roads where public or administrative use exists. Designate FR 100 and FR 089 to open to all off-highway vehicles.
Recreation management
Comment Period
05/24/2018
Decision
09/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Trail Management; Travel Management |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 9/12/2018
East and northeast of Cove Fort. · Sevier, Utah
The Fishlake National Forest is proposing to grant the University of Utah a research permit which will allow them to drill two scientific boreholes for thermal gradient, fluid samples and rock chips east of Cove Fort. Existing roads will be used.
Minerals and geology
Decision
09/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Portions of T25N R6W Sec.20 and T25N R6W Sec.05 |
Environmental Assessment · Fremont River Ranger District · updated 8/9/2018
UM Creek drainage, Black Flat crossing · Sevier, Utah
Move TR 2043 out of riparian area: decommission 0.4 mi FR043 and TR 2043, install 3 bridges, culvert and vehicle barriers; convert 0.6 mi TR 2043 to non-motorized; add 1.3 mi newly rerouted FR043.
Recreation managementWildlife, fish, rare plantsRoad managementWatershed management
Comment Period
10/29/2014
Decision
08/2016 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Dispersed Recreation Mgmt.; Species Habitat Improvements; Trail Management; Road Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T24S, R3E, and Sections 17, 20, 29, 32 and 33 SLB&M |
Environmental Assessment · Beaver Ranger District · updated 5/14/2018
The project is located in the south east corner of the Beaver Ranger District. It is boarded to the north by SR-153 and to the south and west by BLM intermixed with private parcels and state sections. · Beaver, Utah
The Beaver Ranger District of the Fishlake National Forest is preparing an environmental assessment to analyze the potential effects of thinning and burning within the 42,900 acre South Beaver project area.
Forest productsWildlife, fish, rare plantsVegetation management (other than forest products)Fuels management
Comment Period
10/05/2017
Objection Period Start
03/22/2018
Decision
05/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Special Products Sales |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Beaver Ranger District · updated 4/17/2018
Upper Beaver Creek, Piute County · Piute, Utah
In accordance with mining law the Fishlake National Forest is preparing an EA to evaluate the potential effects of mining the Jim and Iver claims as described in the plan of ops. This include reopening a collapsed adit and taking geologic samples.
Minerals and geology
Comment Period
06/05/2013
Decision
06/2015 (Estimated)
Implementation
08/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T27S R 5W Sec 25 |
Environmental Assessment · Fremont River Ranger District · updated 3/20/2018
Half mile from Fish Lake approximately 10 miles north of Loa, UT · Sevier, Utah
Promote aspen regeneration. Thin and salvage conifers.
Vegetation management (other than forest products)
Comment Period
04/28/2010
Decision
05/2021 (Estimated)
Implementation
05/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage) |
| Decision Memo Pole Canyon Vegetation Treatment Project | Decision Signed Date: 12/09/2009 (FS Withdrawn, Reversed in Appeal (215)) Legal Notice Date: 12/16/2009 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R2E S 13,14,15 and T26S R3E S18 |
Environmental Impact Statement · R4 - Intermountain Region All Units · updated 3/20/2018
This project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, Utah, and Nevada. · Beaver; Duchesne; Emery; Garfield; Iron; Juab; Millard; Piute; Sevier; Uintah; Wasatch; Weber, Utah
This proposed 600 kV direct current transmission line is designed to carry renewable energy (primarily wind power) from generation sources in central Wyoming to markets in in the pacific southwest
Special use management
NOI in Federal Register
01/04/2011
DEIS NOA in Federal Register
02/18/2011
FEIS NOA in Federal Register
01/13/2017
Objection Period Start
01/21/2017
Decision
05/2017 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Transwest Express Transmission Project | Decision Signed Date: 05/31/2017 |
| Forests | Ashley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Roosevelt Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Ferron Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 10/18/2017
The Mytoge Mountain area approx. 0.7 miles East of Fish Lake and approx. 10 miles from Loa, Utah. The legal description includes portions of sections 13,14,15 of T26S R2E. · Sevier, Utah
The Fremont River Ranger District is proposing timber stand improvement treatments and salvage of dead and/or dying trees to reduce undesirable species, improve species diversity, and maximize successful reforestation.
Vegetation management (other than forest products)Forest products
Decision
10/2017 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 9/12/2017
Located within the North Fork of North Creek drainage. Township 28s, Range 6W, Section 29 · Beaver, Utah
Construction of a fish barrier to improve the security of an existing native Bonneville cutthroat trout (BCT) population. The fish barrier is proposed for construction on the lower end of the North Fork of North Creek.
Wildlife, fish, rare plants
Decision
09/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 8/30/2017
Proposed action is on the Beaver Ranger District of the Fishlake National Forest located approximately 8.5 miles up Beaver Canyon, along the Beaver River. · Beaver, Utah
Reconstruct the existing 20ft X 20ft hydro Plant #3 building to approximately 35ft X 20ft and upgrade the current generator to a Pelton Generator.
Special use management
Decision
08/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Richfield Ranger District · updated 8/16/2017
The seismic line would be located in the West half of the South West quarter of Sec. 14 and the South half of Sec. 15, T.21S. R.4E. immediately adjacent to the Sufco Mine federal coal lease. · Sevier, Utah
The Richfield District Ranger is evaluating a proposal from Canyon Fuel Company LLC, Sufco Mine, to conduct a high resolution seismic reflection survey to identify potential faulting adjacent to the current Sufco underground mine operations.
Minerals and geology
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 8/15/2017
The proposed expansion project is located along Utah State Route 25 at the northwest end of Fish lake in south-central Sevier County, Utah. It is located in Section 9, Township 26S, Range 2E. · Sevier, Utah
Expand Bowery Haven Resort facilities to meet demonstrated public need. Proposed expansion includes new construction or expansion to the following: employee housing, laundry building, picnic pavilion, cafe, general store, RV park and water pipeline.
Special use management
Comment Period
04/20/2017
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| Bowery Haven Resort Expansion Project 51695 | Decision Signed Date: 08/15/2017 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 7/20/2017
Project is located across approximately 75,000 acres of the Fishlake National Forest, and the old Teasdale Ranger District of the Dixie National Forest. · Beaver; Millard; Piute; Sevier; Wayne, Utah
The Fishlake National Forest is proposing stand improvements or wildlife habitat improvements designed to remove undesirable conifer cover from encroached habitats.
Wildlife, fish, rare plants
Decision
07/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Uinta-Wasatch-Cache All Units · updated 7/19/2017
The project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, and Utah. Project terminates at the Mona substation in central Utah. · Beaver; Duchesne; Emery; Garfield; Iron; Juab; Millard; Piute; Sevier; Uintah; Wasatch; Weber, Utah
This proposed 500 kV transmission line is designed to deliver power to Rocky Mountain Power utility costumers in Utah and the intermountain west. Generation sources are located in central Wyoming.
Special use management
NOI in Federal Register
04/01/2011
DEIS NOA in Federal Register
04/01/2011
FEIS NOA in Federal Register
01/13/2017
Objection Period Start
01/21/2017
Decision
05/2017 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Energy Gateway South Transmission Project | Decision Signed Date: 05/31/2017 |
| Forests | Ashley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Duchesne Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Price Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 7/18/2017
Proposed action is on the Beaver Ranger District of the Fishlake National Forest located approximately 8.5 miles up Beaver Canyon, along the Beaver River. · Beaver, Utah
This project has been cancelled. This is a duplicate project, please refer to project number 51916 - Beaver City Hydro Plant #3.
Special use management
Scoping Start
06/2017 (Estimated)
Decision
06/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Beaver Ranger District · updated 2/21/2017
East of the town of North Creek in Beaver County Utah. Barriers will be constructed on National Forest System lands near the South Fork of North Creek Trialhead, Forest Trail 062. · Beaver, Utah
The Utah Division of Wildlife Resources is proposing to construct 2 fish barriers as part of Bonneville Cutthroat Trout restoration efforts utilizing natural materials. The FS and DWR are working together to implement conservation of native trout.
Wildlife, fish, rare plants
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fillmore Ranger District · updated 2/8/2017
South end of Fillmore Ranger District north of I70 · Millard, Utah
Mechanical treatment (i.e., chain harrow) of sagebrush communities in various areas totaling approximatley 5000 acres on the southern portion of the Fillmore Ranger District north of I70.
Wildlife, fish, rare plantsGrazing managementVegetation management (other than forest products)Fuels management
Comment Period
11/24/2016
Decision
02/2017 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Rangeland Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 2/3/2017
Mytoge Mountain to Tidwell Slopes area along the Fishlake NF boundary and Highway 72. The legal description of the analysis area includes all or portions of T25S, R3-4; T26S, R1-4E; and T27S, R3-4E. · Sevier, Utah
The Fishlake National Forest, Fremont River Ranger District is proposing to reduce conifer canopy cover within sage-grouse seasonal and lek sagebrush habitat.
Wildlife, fish, rare plants
Comment Period
11/17/2016
Decision
02/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 12/29/2016
The southwest lake side end of Fish Lake, which can be accessed by Utah State Route 25. · Sevier, Utah
As part of a Fish Lake Resorts llc. master development plan, the permit holder has proposed to upgrade an existing lodge into a two story "eight-plex", expand the existing RV parking area and add a small external outbuilding for equipment storage.
Special use management
Comment Period
06/16/2016
Objection Period Start
11/03/2016
Decision
12/2016 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Fishlake National Forest All Units · updated 9/23/2016
Headwaters of Chalk Creek north of Forest Road 865 between Turner Wash on the south and Mason Gulch on the north. · Millard, Utah
The Natural Resource Conservation Service (NRCS) is proposing to install a SNOTEL weather station in the headwaters of Chalk Creek for the purpose of monitoring snow depth, snow water equivalent data, precipitation, temperature, etc.
Special use management
Decision
09/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T21S R4W S35 SLBM |
Environmental Assessment · Fishlake National Forest All Units · updated 7/25/2016
East of the I-15 corridor between the communities of Fillmore and Holden, Utah. · Millard, Utah
fuels reduction project see attached documents
Fuels management
Comment Period
03/10/2016
Objection Period Start
05/26/2016
Decision
07/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Richfield Ranger District · updated 7/14/2016
Near the small communities of Koosharem and Greenwich on the east side of Monroe Mountain. covering multiple map sections of Ranges 1 and 2 West and in Townships 26, 27 and 28 South. · Piute; Sevier, Utah
Small diameter encroaching Pinyon and Juniper removal on 3,503 acres using non-commercial tree cutting, followed by seeding newly exposed ground with native brush, grasses and forbs
Land management planning
Decision
07/2016 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Multiple sections in Ranges 1 and 2 West and in Townships 26, 27, and 28 South |
Environmental Assessment · Fremont River Ranger District · updated 3/24/2016
Located on the North Slope of the Boulder Mountain, south of Teasdale and Grover, Utah; between Government Point and Chokecherry Point. · Wayne, Utah
Remove, pile and burn small diameter ladder fuels pinion and juniper on approx. 2,673 acres of the Dixie NF's on Boulder Mountain North Slope and limb large diameter ponderosa individuals along various project area routes to create shaded fuel breaks
Fuels management
Comment Period
08/13/2014
Objection Period Start
02/11/2016
Decision
03/2016 (Estimated)
Implementation
01/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 (2013) HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T. 30 S. R. 5 E., Sections 7, 16, 17, 18, 19, 20, 21, 28, and 30; T. 29 S. R. 4 E. Sections 19, 29, 30, 31; and T. 29 S. R. 3 E., Sections 25, 26, 34, and 35; T. 30 S. R. 4 E. Sections 1,2, 3, 9, 10, |
Environmental Assessment · Beaver Ranger District · updated 2/8/2016
The Big Flat Project is located approximately 12 miles east of Beaver, Utah, along state highway 153, from Merchant Valley to Big Flat. · Beaver, Utah
The purpose of this proposal is to: Manage the timber resources on lands suitable for production of saw timber; Use prescribed fire to reduce fuel buildup and meet resource objectives; Improve age class distribution and maintain species diversity.
Fuels managementVegetation management (other than forest products)Forest products
Comment Period
12/17/2014
Objection Period Start
12/09/2015
Decision
02/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 7/13/2015
West of Fish Lake near Na-Gah Flat on Fishlake High-Top · Sevier, Utah
Treat vegetation to improve stand structure and diversity, improve spruce resilience to insect and disease,improve aspen regeneration, and provide a wood fiber product for public use.
Vegetation management (other than forest products)Forest products
Comment Period
04/09/2014
Objection Period Start
04/22/2015
Decision
06/2015 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R1E sections 2, 11-15, 22-23 |
Decision Memo · Beaver Ranger District · updated 2/9/2015
The Little Res II project is located seven miles east of Beaver, Utah in the vicinity of Little Reservoir. The project area is approximately 1,290 acres in size and abuts 780 acres of private land. · Beaver, Utah
The proposal consists of two stand improvement treatments: Noncommercial tree cutting and prescribed fire. A stand improvement is an intermediate treatment made to improve the composition, structure, condition, health, and growth forest stands.
Vegetation management (other than forest products)
Decision
02/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Fremont River Ranger District · updated 11/4/2014
Splatter Canyon approx 1/4 mile west of Forest Road #036 and approx 5 miles northwest of Mill Meadow Reservoir, Sevier County, Utah. NE 1/4 of the NW 1/4 of Section 8, T26S, R3E, SLBM · Sevier, Utah
Authorize excavation of aggregate material at the previously reclaimed splatter Canyon Gravel Pit, improve 1/4 mile of road from Forest Road #036 to the pit for 2-way traffic, and operation of a temporary asphalt plant adjacent to the pit
Minerals and geologySpecial use management
Comment Period
04/30/2014
Objection Period Start
06/05/2014
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Richfield Ranger District · updated 7/9/2014
Convulsion Canyon south of the SUFCO coal mine · Sevier, Utah
SUFCO Mine has requested approval to expand use under an existing special use permit through the addition of 19 acres for coal load out facilities and coal storage piles. This action would allow for coal segregation by quality to meet customer needs
Minerals and geologySpecial use management
Comment Period
03/19/2014
Objection Period Start
05/14/2014
Decision
07/2014 (Estimated)
Implementation
08/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Section 12, Township 22 South, Range 4 East, SLBM, Sevier County, Utah |
Decision Memo · Fillmore Ranger District · updated 6/18/2014
Mouth of Dry Creek near Oak City Utah. Debris Basin will be constructed below Forest Road 416 due east of the forest gate. · Millard, Utah
The Fillmore Ranger District has received an application for a Special Use Permit from Millard County for the purpose of constructing and maintaining a debris basin on National Forest System lands in Dry Creek for the purpose of flood control.
Watershed managementSpecial use management
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Dry Creek Debris Basin Decision Memo | Decision Signed Date: 06/11/2014 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | Township 17S Range 4W Section 9 |
Decision Memo · Fremont River Ranger District · updated 4/21/2014
Sand Creek drainage, near FR 207 between Birch Springs and teh junction of FR 207 and FR 1597 · Wayne, Utah
Installation of a chlorination system including burial of 500 gallon propane tank, concrete vault, and non-reflective fence covering an area 20 feet by 22 feet.
Special use management
Decision
02/2014 (Estimated)
Implementation
03/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Torrey Town Chlorination System Project | Decision Signed Date: 02/03/2014 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | NE 1/4, Section 34, T28S,R4E, SLBM |
Environmental Impact Statement · Fishlake National Forest All Units · updated 11/1/2013
Fishlake National Forest · Beaver; Garfield; Iron; Juab; Millard; Piute; Sanpete; Sevier; Wayne, Utah
As required by the Federal Onshore Oil and Gas Leasing Reform Act of 1987 the responsible officials of the Forest Service and BLM will evaluate lands administered by the Fishlake National Forest for oil and gas leasing.
Minerals and geology
NOI in Federal Register
01/18/2011
DEIS NOA in Federal Register
02/17/2012
FEIS NOA in Federal Register
08/30/2013
Decision
08/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 219 (1982) |
| Project Activity | Land Use Adjustments; Plan Amendment |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Richfield Ranger District · updated 11/1/2013
Approximately 4 miles NE of Oak City, Utah · Millard, Utah
Request from Millard County to obtain rock material to construct gabions and other erosion control devices to be used to protect municipal water developments and associated structures.
Special use managementWatershed management
Comment Period
02/27/2013
Decision
09/2013 (Estimated)
Implementation
03/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations; Watershed Improvements |
| Millard county Mineral Materials Permit | Decision Signed Date: 09/30/2013 Legal Notice Date: 09/30/2013 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T15S R4W Sec. 24 |
Environmental Assessment · Fremont River Ranger District · updated 9/27/2013
North slope of Boulder Mountain · Garfield; Wayne, Utah
This project would use mechanical treatments and fire to reduce fuel loading and decrease fire danger on approximately 4000 acres of NFS lands. The vegetation type to be treated is pinyon/juniper along the north slope of Boulder Mountain.
Fuels managementWildlife, fish, rare plantsVegetation management (other than forest products)
Comment Period
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| DN and FONSI Boulder Foothills Fuels Reduction Projects | Decision Signed Date: 01/27/2012 (FS Withdrawn) Legal Notice Date: 02/01/2012 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
Environmental Assessment · Richfield Ranger District · updated 9/27/2013
Adjacent to the private land in-holdings of Salina Creek/Accord Lakes · Sevier, Utah
Ecosystem restoration project aimed at improving native species diversity, improving wildlife habitat, and reducing hazardous fuel loadings adjacent to the mountain communities in Salina Creek and Accord Lakes.
Fuels managementVegetation management (other than forest products)
Comment Period
01/11/2012
Decision
09/2013 (Estimated)
Implementation
11/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Salina Creek Ecosystem Restoration Project DN/FONSI | Decision Signed Date: 09/16/2013 Legal Notice Date: 09/18/2013 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T21S R4E S16; T21S R3E Sections 25, 30, 31, 35, 36; T21S R4E Sections 27, 28, 32, 33, 34; T21S R4E Sections 23, 24, 25, 26 and T22S R4E Sections 1, 2, 3, 10, 11, and 12 |
Decision Memo · Fremont River Ranger District · updated 9/27/2013
Torrey, Utah · Wayne, Utah
Relocate the Sand Creek Trailhead from current location approximately 0.7 miles along existing road to the NE. Project proposal is in response to public concerns over current location and conflicts between land owners and user groups
Road managementRecreation management
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Maintenance; Road Maintenance; Road Improvements/Construction; Travel Management |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T29S R4E Sec 2 |
Environmental Assessment · Beaver Ranger District · updated 8/1/2013
Headwaters of Indian Creek, N. Fork of North Creek, and Shingle Creek drainages · Beaver; Piute, Utah
Treat approximately 955 acres of burned timber within the Twitchell Canyon wildfire perimeter to to accelerate the recovery of the project area from the impacts of the Twitchell Fire.Proposed treatments include timber harvest and reforestation.
Forest products
Comment Period
04/03/2013
Decision
07/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Salvage) |
| Twitchell Fire Salvage Sale Project | Decision Signed Date: 07/29/2013 Legal Notice Date: 07/31/2013 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
Decision Memo · Fishlake National Forest All Units · updated 6/28/2013
Approximately 3 miles West of Joseph, Utah · Sevier, Utah
Joseph Town has identified a current and projected future need for additional water storage to ensure consistent water supply for its customers. To meet the storage needs installation of a 200,000 gallon storage tank is being proposed.
Special use management
Comment Period
12/19/2012
Decision
06/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Decision Memo Joseph Town Water Storage Tank | Decision Signed Date: 06/14/2013 Legal Notice Date: 06/26/2013 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
Decision Memo · Beaver Ranger District · updated 6/28/2013
Clear Creek in Sevier County below confluence with Pole Canyon and above the Narrows · Sevier, Utah
The Utah Division of Wildlife Resouces has proposed construction of a fish barrier in Clear Creek on the Beaver Ranger District to aid in the restoration of native Bonneville cutthroat trout.
Wildlife, fish, rare plants
Comment Period
04/17/2013
Decision
06/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Species Population Enhancements |
| Decision Memo Middle Clear Creek Fish Barrier Project | Decision Signed Date: 06/21/2013 Legal Notice Date: 06/26/2013 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
Decision Memo · Fishlake National Forest All Units · updated 6/28/2013
Sunflower Flat, Boulder Mountain · Garfield, Utah
The Fishlake NF is proposing to issue a special use permit to the Natural Resource Conservation Service (NRCS) to install a SNOTEL site in Sunflower Flat on the Boulder Mountain. The weather station will be used to collect hydro-climatic data.
Special use management
Comment Period
02/06/2013
Decision
04/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Decison Memo Sunflower SNOTEL Project | Decision Signed Date: 04/25/2013 Legal Notice Date: 05/01/2013 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
Environmental Assessment · Richfield Ranger District · updated 5/3/2013
Monroe Mountain , Fishlake National Forest · Piute; Sevier, Utah
Construct one mile of fence and add a water distribution system to allotments on Monroe Mountain for the purposes of improved livestock distribution, increased rangeland rest, and decreased browsing impacts to aspen.
Vegetation management (other than forest products)Grazing management
Comment Period
09/17/2012
Decision
04/2013 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Grazing Allotment Management; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| DN/FONSI Monroe Mountain Livestock Management Improvement Project | Decision Signed Date: 04/29/2013 Legal Notice Date: 05/01/2013 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Townships 26, 27, & 28 S, Ranges 1, 2, & 3 W |
Decision Memo · Fishlake National Forest All Units · updated 4/29/2013
Oak Creek, Boulder Mountain · Garfield, Utah
Establish a new trailhead to access the High Ranger Trail. Current access requires hikers and equestrian users to cross a busy highway on a blind corner. Proposal is to move trailhead near existing parking area that is safe and convienent for users.
Recreation management
Comment Period
02/06/2013
Decision
04/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| DM Oak Creek Trailhead Relocation Project | Decision Signed Date: 04/15/2013 Legal Notice Date: 04/17/2013 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
Environmental Assessment · Richfield Ranger District · updated 1/17/2013
Adjacent to main portal of SUFCO Mine in Sevier County, Utah on the Richfield Ranger District · Sevier, Utah
The BLM received a request to add 20 acres to coal lease #UTSL-062583. Authorization of the requested modification requires consent from FS with required non-mineral resource protection stipulations.
Minerals and geology
Comment Period
12/05/2012
Decision
01/2013 (Estimated)
Implementation
02/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| DN/FONSI SUFCO 20 ACRE LEASE MODIFICATION TO FEDERAL COAL LEASE UTSL-062583 | Decision Signed Date: 01/16/2013 (Reversed in Appeal (215)) Legal Notice Date: 01/16/2013 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | W ½ NW ¼ SW ¼ Sec. 12 T22S R4E SLBM |
Environmental Impact Statement · Pine Valley Ranger District · updated 12/21/2012
Linear alignment from approximately 6 miles northeast of Richfield, UT to just southwest of the town of Central, UT · Beaver; Iron; Millard; Sevier; Washington, Utah
Construct a new 345 kV transmission line connecting the Sigurd substation located near Richfield, UT to the Red Butte substation located near Central, UT.
Special use management
NOI in Federal Register
01/05/2010
DEIS NOA in Federal Register
06/03/2011
FEIS NOA in Federal Register
10/05/2012
Decision
12/2012 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Sigurd to Red Butte No. 2 - 345kV Transmission Project Record of Decision | Decision Signed Date: 12/07/2012 Legal Notice Date: 12/12/2012 |
| Forests | Dixie National Forest; Fishlake National Forest |
| Districts | Pine Valley Ranger District; Fillmore Ranger District; Beaver Ranger District |
Environmental Assessment · Fremont River Ranger District · updated 11/26/2012
1.5 miles soutwest of Bicknell, Utah · Wayne, Utah
Maintain 4 springs to meet state water quality standards, add 5th spring to the system to meet use needs, replace water delivery line from springs to city and add a storage tank/treatment facility to the system.
Special use management
Comment Period
09/05/2012
Decision
10/2012 (Estimated)
Implementation
11/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| DN/FONSI Bicknell Town Water Improvement Project | Decision Signed Date: 10/18/2012 Legal Notice Date: 11/14/2012 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
Environmental Assessment · Fillmore Ranger District · updated 7/19/2012
North of Interstate 70 west of Fremont Indian State Park · Sevier, Utah
Proposal would be to harvest a locatable mineral using surface mining techniques affecting approximately 35 acres of National Forest System lands. Operations would include development of a haul road and material transfer area
Minerals and geology
Comment Period
03/14/2012
Decision
05/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations; Special Products Sales |
| Green Solutions Mining Operations DN/FONSI | Decision Signed Date: 05/15/2012 Legal Notice Date: 05/16/2012 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T 25S R 4 W within portions of sections 19, 29 and 30 |
Environmental Impact Statement · WO - Washington Office - National headquarters · updated 7/10/2012
11 contiguous Western States (Arizona, California, Colorado, Idaho, Montana, New Mexico, Nevada, Oregon, Utah, Washington, and Wyoming) and Alaska. · Bonner; Aleutians East; La Paz; Columbia; Coos; Colusa; Denver; Douglas, Alaska; Arizona; California; Colorado; District of Columbia; Idaho; Kansas; Montana; North Dakota; Nebraska; New Mexico; Nevada; Oklahoma; Oregon; South Dakota; Texas; Utah; Washington; Wyoming
The Forest Service was a cooperating agency, assisting the Bureau of Land Management (BLM) in that Agency's geothermal leasing analysis and decision. The BLM issued a record of decision on 12/17/2008.
Regulations, directives, orders
NOI in Federal Register
06/13/2007
DEIS NOA in Federal Register
06/13/2008
FEIS NOA in Federal Register
10/24/2008
Decision
02/2010 (Estimated)
Implementation
03/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Regulation Creation/Modification |
| Forests | Beaverhead-Deerlodge National Forest; Bitterroot National Forest; Clearwater National Forest; Custer National Forest; Custer Gallatin National Forest; Helena National Forest; Lewis And Clark National Forest; Lolo National Forest; Nez Perce-Clearwater National Forest; Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Rio Grande National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Apache-Sitgreaves National Forests; Carson National Forest; Cibola National Forest; Coronado National Forest; Gila National Forest; Lincoln National Forest; Santa Fe National Forest; Tonto National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Payette National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest; Angeles National Forest; Cleveland National Forest; Eldorado National Forest; Inyo National Forest; Klamath National Forest; Lassen National Forest; Los Padres National Forest; Mendocino National Forest; Modoc National Forest; Plumas National Forest; San Bernardino National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest; Tahoe National Forest; Deschutes National Forest; Fremont-Winema National Forest; Gifford Pinchot National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Mt. Hood National Forest; Ochoco National Forest; Rogue River-Siskiyou National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Willamette National Forest; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
| Districts | Beaverhead-Deerlodge National Forest All Units; Bitterroot National Forest All Units; Clearwater National Forest All Units; Custer National Forest All Units; Custer Gallatin National Forest; Custer Gallatin National Forest All Units; Helena National Forest All Units; Lewis And Clark National Forest All Units; Lolo National Forest All Units; Nez Perce-Clearwater National Forest All Units; Grand Mesa Uncompahgre and Gunnison National Forest All Units; Medicine Bow-Routt National Forest All Units; Rio Grande National Forest All Units; Arapaho and Roosevelt National Forests All Units; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands All Units; San Juan National Forest All Units; White River National Forest All Units; Apache-Sitgreaves National Forests All Units; Carson National Forest All Units; Cibola National Forest All Units; Coronado National Forest All Units; Gila National Forest All Units; Lincoln National Forest All Units; Santa Fe National Forest All Units; Tonto National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Payette National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units; Angeles National Forest All Units; Cleveland National Forest All Units; Eldorado National Forest All Units; Inyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Los Padres National Forest All Units; Mendocino National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; San Bernardino National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units; Tahoe National Forest All Units; Deschutes National Forest All Units; Fremont-Winema National Forest All Units; Gifford Pinchot National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Mt. Hood National Forest All Units; Ochoco National Forest All Units; Rogue River-Siskiyou National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Willamette National Forest All Units; R10 - Alaska Region All Units; WO - Washington Office - National headquarters |
Environmental Assessment · Richfield Ranger District · updated 4/27/2012
5 miles SE of Salina Utah on Triangle Mountain south of Interstate 70 · Sevier, Utah
Construct 180 foot tall free standing tower and equipment on Triangle Mountain to provide wireless service along Interstate 70 and surrounding area; includes approximately 3 miles of power line.
Special use management
Comment Period
02/22/2012
Decision
04/2012 (Estimated)
Implementation
06/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Plan Amendment |
| DN/FONSI Triangle Mountain Communications Site and Forest Plan Amendment | Decision Signed Date: 04/27/2012 Legal Notice Date: 04/27/2012 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T22S R2E S11 / 38 54 44.15 N 111 46 12.48W DMS |
Decision Memo · Fillmore Ranger District · updated 3/28/2012
North Fork of Corn Creek · Millard, Utah
Installation of 2 stream structures to create barriers that limit non native fish movement into Bonneville Cutthroat Trout habitat.
Wildlife, fish, rare plants
Decision
03/2012 (Estimated)
Implementation
06/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Decison Memo North Fork Corn Creek Fish Barrier Project | Decision Signed Date: 03/14/2012 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
Decision Memo · Fremont River Ranger District · updated 3/28/2012
South end of Fishlake Basin near Doctor Creek Campground · Sevier, Utah
Provide protection for and increase regeneration of the Pando aspen clone. Project may include fencing of stands to protect regenerating aspen suckers and aspen regeneration techniques to promote new growth.
Vegetation management (other than forest products)
Decision
02/2012 (Estimated)
Implementation
03/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Decision Memo Pando Aspen Clone Restoration Project | Decision Signed Date: 02/02/2012 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T 26S R 1E Sections 24 & 25 |
Decision Memo · Beaver Ranger District · updated 11/8/2011
East of Little Reservoir to the South Fork of Beaver River · Beaver, Utah
Existing pipeline that transfers water from the South Fork of Beaver River to Little Reservoir is deteriorating and needs to be replaced. Replacement pipe would be laid in the existing corridor.
Recreation managementWildlife, fish, rare plants
Decision
11/2011 (Estimated)
Implementation
01/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Decision Memo Little Reservoir Pipeline Replacement | Decision Signed Date: 11/07/2011 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
Decision Memo · Beaver Ranger District · updated 9/26/2011
Approximately 24 miles east of Beaver, Utah and approximately 1 mile SSW of Lebaron Lake in the Dry Hollow drainage of Circleville Mountain · Beaver, Utah
Commercial salvage and sanitiation of spruce beetle infested and and adjacent uninfested trees necessary to control the spread of beetle outbreak within approximately 244 acres in the Dry Hollow drainage of Circleville Mountain.
Forest products
Decision
09/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (14), 36 Cfr 220.6(E)(14) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T30S R5W Secs 10 and 15 SLBM |
Environmental Assessment · Beaver Ranger District · updated 4/13/2011
Project boundary extends from Hwy 153 to Manderfield encompassing NFS lands along west facing front range of the district · Beaver, Utah
Hazardous fuels reduction project
Fuels managementVegetation management (other than forest products)
Comment Period
08/04/2010
Decision
04/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Decision Notice and FONSI North Beaver Fuels Project | Decision Signed Date: 04/04/2011 Legal Notice Date: 04/06/2011 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
Environmental Assessment · Richfield Ranger District · updated 2/23/2011
Swift Spring located on West side of Foreshea mountain · Piute, Utah
The project would develop Swift Spring and distribute the water, via pumps and pipes, to several new and existing cattle watering locations across the Kingston and Foreshea Alloments.
Grazing management
Comment Period
05/05/2010
Decision
02/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management; Grazing Structural Improvements |
| Decison Notice/FONSI Swift Springs Water Development Project | Decision Signed Date: 02/18/2011 Legal Notice Date: 02/23/2011 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
Decision Memo · Fremont River Ranger District · updated 12/30/2010
One tenth of a mile from Johnson Reservoir. Approximately 13.7 miles North/Northeast of Loa, UT · Sevier, Utah
Induce aspen regeneration due to current stand mortality.
Vegetation management (other than forest products)
Decision
02/2011 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T25S R2E S25 and T25S R3E S30&31 |
Environmental Assessment · Richfield Ranger District · updated 9/2/2010
The south end of Monroe Mountain, Richfield Ranger District, Fishlake National Forest · Piute, Utah
Prescribed burn within 5,169 acres and mechanically treat 578 acres with Dixie Harrow. The proposed action is designed to reduce hazardous fuels within the area, restore aspen ecosystem health and regeneration and improve wildlife habitat.
Wildlife, fish, rare plantsFuels management
Comment Period
07/14/2010
Decision
08/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements |
| Twin Peaks Hazardous Fuels Reduction Project Decision Notice/FONSI | Decision Signed Date: 08/30/2010 Legal Notice Date: 09/01/2010 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T28S, R2½ W, Sections 26, 27, 35 & 36; T29S R2½W, Sections 1,11,12,13,14,15,22,23,24,25,26 and 27; and T29S, R2W, Sections 18,19, & 30 |
Decision Memo · Fillmore Ranger District · updated 6/29/2010
Approximately 5 miles north of the Junction of Interstate 70 and Interstate 15 and Cove Fort · Millard, Utah
Fillmore Ranger district proposes provide water sources on National Forest System land, away from Interstate 15, reducing the number of elk and deer encroching on the Interstate, resulting in reduced big game/vehicle accidents.
Wildlife, fish, rare plants
Comment Period
09/02/2009
Decision
04/2010 (Estimated)
Implementation
06/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| DN & FONSI Dog Valley Water Development Project | Decision Signed Date: 04/14/2010 Legal Notice Date: 04/14/2010 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
Decision Memo · Richfield Ranger District · updated 3/31/2010
Approx. 4-5 miles NE of Salina, north of I70 and south of the Willow Creek road (001) · Sevier, Utah
Install 5-10 wildlife guzzlers across the Cedar Mountain area to provide enough water to support deer, elk, turkey, chukar and grouse. Guzzler installation would consist of catch apron approximately 20 feet of pipe and a trough.
Wildlife, fish, rare plants
Comment Period
12/23/2009
Decision
02/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| Decison Memo Cedar Mountain Guzzler Project | Decision Signed Date: 02/16/2010 Legal Notice Date: 02/16/2010 |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T21S, R1E, Sec. 23-27,35 |
Environmental Assessment · Richfield Ranger District · updated 3/31/2010
Monroe Mountain near Indian Peak and Monument Peak · Sevier, Utah
This project would treat approximately 3650 acres (3036 prescribed fire and 615 of mechanical) to reduce fuels near private property and a Forest Service Guard Station. Merchantable timber could be commercially removed.
Fuels managementVegetation management (other than forest products)Forest products
Comment Period
07/29/2009
Decision
03/2010 (Estimated)
Implementation
08/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | T25S, R1W, Sec. 31; T25S R2W, Secs. 11, 12, 13, and 24; and T26S, R1W, Secs. 4 - 8, and 17 - 21 |
Environmental Impact Statement · Richfield Ranger District · updated 11/24/2009
Convulsion Canyon · Sevier, Utah
Project would upgrade existing road/trail to provide a shorter and alternate access route from SUFCO Mine to Hwy 10. Appx 2.4 miles of 28' wide pavement across National Forest System lands and several miles of Public Lands administered by the BLM.
Special use managementMinerals and geology
NOI in Federal Register
01/01/1999
DEIS NOA in Federal Register
11/30/2001
FEIS NOA in Federal Register
01/27/2006
Decision
03/2006 (Estimated)
Implementation
04/2006 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| Forests | Fishlake National Forest |
| Districts | Richfield Ranger District |
| Legal Land Description | Township 22 South, Range 4 East, Sections 12 & 13 & Township 22 South, Range 5 East, Section 18 |
Environmental Impact Statement · Fishlake National Forest All Units · updated 6/15/2007
Allotments on the Beaver Ranger District · Beaver; Garfield; Iron; Millard; Piute; Sevier, Utah
The project would evaluate the environmental effects of reissuing 10-year term grazing permits to continue to authorize grazing on eleven grazing allotments on the Beaver Ranger District in central Utah.
Grazing management
NOI in Federal Register
03/11/2004
DEIS NOA in Federal Register
09/03/2004
DEIS NOA in Federal Register
09/2004 (Estimated)
FEIS NOA in Federal Register
12/22/2006
Decision
01/2007 (Estimated)
Implementation
02/2007 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management; Grazing Authorizations |
| Reissuance of Term Grazing Permits on Eight Cattle Allotments | Decision Signed Date: 01/16/2007 Legal Notice Date: 01/17/2007 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
Environmental Impact Statement · Fishlake National Forest All Units · updated 12/29/2006
Forest-wide · Beaver; Garfield; Iron; Juab; Millard; Piute; Sanpete; Sevier; Wayne, Utah
The project would improve management and enforcement of the off-highway vehicle travel policy on the Forest. This will include a Forest Plan amendment.
Recreation management
NOI in Federal Register
06/07/2004
DEIS NOA in Federal Register
08/05/2005
FEIS NOA in Federal Register
12/22/2006
Decision
12/2006 (Estimated)
Implementation
12/2006 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management; Travel Management |
| Fishlake National Forest OHV Route Designation | Decision Signed Date: 12/12/2006 |
| Forests | Fishlake National Forest |
| Districts | Fishlake National Forest All Units |
Environmental Assessment · Beaver Ranger District · updated 3/21/2006
Interstate 70 between Cove Fort and Fremont Indian State Park · Sevier, Utah
This project would designatte two wireless telecommunications sites, along I-70 between Cove Fort and Fremont Indian State Park, with primary purpose of serving cellular, personal communications services and enhanced specialized mobile radio.
Special use management
Comment Period
08/31/2005
Decision
01/2006 (Estimated)
Implementation
03/2006 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Special Use Authorizations |
| I-70 Wireless Communications Site | Decision Signed Date: 01/09/2006 Legal Notice Date: 01/18/2006 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |