Fish Lake Resorts proposes to demolish their existing marina building and replace with one slightly larger (20' x 40')approximately 30 feet southeast of the existing building. A larger marina structure is needed to provide services for the marina.
Location
Fish Lake Basin at Lakeside Marina
Project timeline
1
Scoping Start
02/09/2022
2
Decision
06/2022 (Estimated)
3
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lakeside Marina Building Replacement | Decision Signed Date: 06/22/2022 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | T26S R2E Section 19 |