This project has been cancelled. This is a duplicate project, please refer to project number 51916 - Beaver City Hydro Plant #3.
Location
Proposed action is on the Beaver Ranger District of the Fishlake National Forest located approximately 8.5 miles up Beaver Canyon, along the Beaver River.
Project timeline
1
Scoping Start
06/2017 (Estimated)
2
Decision
06/2017 (Estimated)
3
Implementation
07/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | Not Applicable |