The Fremont River Ranger District proposes to construct a fish passage barrier on UM Creek between Mill Meadow and Forsyth Reservoirs. The barrier built of boulders on site will protect the Colorado River cutthroat trout population in the stream.
Location
T26S R3E Sec35
Project timeline
1
Scoping Start
02/20/2020
2
Decision
05/2020 (Estimated)
3
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| UM Creek Fish Passage Barrier | Decision Signed Date: 05/20/2020 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |