Proposal would be to harvest a locatable mineral using surface mining techniques affecting approximately 35 acres of National Forest System lands. Operations would include development of a haul road and material transfer area
Location
North of Interstate 70 west of Fremont Indian State Park
Project timeline
1
Scoping Start
08/03/2011
2
Comment Period
03/14/2012
3
Decision
05/2012 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations; Special Products Sales |
| Green Solutions Mining Operations DN/FONSI | Decision Signed Date: 05/15/2012 Legal Notice Date: 05/16/2012 |
| Forests | Fishlake National Forest |
| Districts | Fillmore Ranger District |
| Legal Land Description | T 25S R 4 W within portions of sections 19, 29 and 30 |