Decision Memo Completed

DT Upper Carissa Road

Fishlake National Forest Piute, Utah Beaver Ranger District

DT Mining LLC has proposed a .9 mile extension of FS Road 1108. The extension would follow a previously decommissioned route. The project would consist of grading the entire .9 miles and widening of the road in needed locations.

Location

Near Deer Trail Mountain. Approximately 5 miles south of Marysvale, Utah.

Project timeline

1
Scoping Start
01/11/2023
2
Decision
03/2023 (Estimated)
3
Implementation
05/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations; Road Improvements/Construction
DT Upper Carissa RoadDecision Signed Date: 03/09/2023
ForestsFishlake National Forest
DistrictsBeaver Ranger District
Legal Land DescriptionT28S, R4W, Sections 13 & 14, Salt Lake Meridian
Minerals and geology