Rebuild the existing DWR cabin on NFS land. The proposed project consists of removing the existing cabin, building a new cabin with a deck, improving the parking lot, and installing a new water line.
Location
Along State Route 24 on the west side of Fish Lake in south-central Utah
Project timeline
1
Scoping Start
05/05/2021
2
Decision
06/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Utah Department of Wildlife Fish Lake Cabin Rebuild | Decision Signed Date: 06/02/2021 |
| Forests | Fishlake National Forest |
| Districts | Fremont River Ranger District |
| Legal Land Description | Not Applicable |