In accordance with mining law the Fishlake National Forest is preparing an EA to evaluate the potential effects of mining the Jim and Iver claims as described in the plan of ops. This include reopening a collapsed adit and taking geologic samples.
Location
Upper Beaver Creek, Piute County
Project timeline
1
Scoping Start
06/05/2013
2
Comment Period
06/05/2013
3
Decision
06/2015 (Estimated)
4
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Jim and Iver #1 and 2 Mining Claims Plan of Operations | Decision Signed Date: 06/10/2015 |
| Forests | Fishlake National Forest |
| Districts | Beaver Ranger District |
| Legal Land Description | T27S R 5W Sec 25 |