Environmental Assessment Completed

Bicknell Culinary Water System Improvement Project

Fishlake National Forest Wayne, Utah Fremont River Ranger District

Maintain 4 springs to meet state water quality standards, add 5th spring to the system to meet use needs, replace water delivery line from springs to city and add a storage tank/treatment facility to the system.

Location

1.5 miles soutwest of Bicknell, Utah

Project timeline

1
Scoping Start
03/20/2012
2
Comment Period
09/05/2012
3
Decision
10/2012 (Estimated)
4
Implementation
11/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFacility Improvements/Construction; Special Use Authorizations; Facility Maintenance
DN/FONSI Bicknell Town Water Improvement ProjectDecision Signed Date: 10/18/2012 Legal Notice Date: 11/14/2012
ForestsFishlake National Forest
DistrictsFremont River Ranger District