USFS proposal to restore stand health, reduce wildfire severity, and promote understory regeneration in sage-steppe, mtn shrub, and aspen communities . Prescribed fire and mechanical treatments would be applied within a 78,000 acre project boundary.
Location
FS boundary that runs from Schellborne Rd south to Kalamazoo Rd
Project timeline
1
Scoping Start
06/05/2009
2
Comment Period
06/09/2010
3
Decision
01/2012 (Estimated)
4
Implementation
05/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| North Schell Restoration Project | Decision Signed Date: 01/10/2012 Legal Notice Date: 01/20/2012 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Ely Ranger District |