Construct 120kV transmission line connecting the Bordertown and California substations.
Location
Appoximately 15 miles west and northwest of Reno, Nevada along the Nevada and California Stateline. North of Interstate 80 near Verdi, Nevada and west of Highway 395 at Bordertown, Nevada.
Project timeline
1
NOI in Federal Register
11/21/2011
2
DEIS NOA in Federal Register
12/12/2014
3
FEIS NOA in Federal Register
06/15/2018
4
Objection Period Start
03/09/2018
5
Decision
06/2019 (Estimated)
6
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Bordertown to California 120kV Transmission Line | Decision Signed Date: 06/14/2019 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Carson Ranger District |
| Legal Land Description | T19N R17E Sec 7. T20N R17E Sec 1,2,6,7,11,12,13,14,18,19, 23, 24,25,26,30,31,35,36 T21N R17E Sec 24,25,34,35,36 T19NR18E Sec 7 .T20N R18E Sec 5,6,7,8,17,18,19,20,29,30,31,32 T21NR18E Sec 4,5,6. |