Proponent plans to add additional telecommunications equipment and facilities to 2 exisitng communcation sites - Pennsylvania Hill Site and Independence Mine Site. Purpose is to provide cellular phone coverage to Northern Elko County.
Location
Pennsylvania Hill Commuincations Site and Indepenence Mine Communications Site
Project timeline
1
Scoping Start
08/22/2012
2
Comment Period
08/22/2012
3
Decision
12/2012 (Estimated)
4
Implementation
01/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Verizon Cellular Projects | Decision Signed Date: 12/07/2012 Legal Notice Date: 12/08/2012 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Mountain City Ranger District |