Project would build key fences to better control and rotate livestock, reducing impacts on riparian areas. This project is being replaced by separate analyses approved under decision memos.
Location
Multiple Locations Accross the Santa Rosa Ranger District
Project timeline
1
Scoping Start
07/30/2013
2
Comment Period
07/30/2013
3
Objection Period Start
03/2016 (Estimated)
4
Decision
06/2016 (Estimated)
5
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Structural Improvements |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Santa Rosa Ranger District |
| Legal Land Description | Not Applicable |