Completing Supplemental Analysis to authorize upgraded to two existing sites and one new site all three are on NFS lands
Location
Sweetwater Commsite, Mean Peak and Wolf Creek
Project timeline
1
Scoping Start
11/26/2014
2
Comment Period
02/18/2015
3
Objection Period Start
05/13/2016
4
Decision
07/2016 (Estimated)
5
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Mountain Warfare Training Center Communications Infrastructure Upgrades Environmental Assesment | Decision Signed Date: 07/12/2016 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Bridgeport Ranger District |
| Legal Land Description | Not Applicable |