Decision Memo Completed

Restoration and Soil Erosion Control for Harris Springs Area

Humboldt-Toiyabe National Forest Clark, Nevada Humboldt-Toiyabe National Forest All Units

Following the 2013 Carpenter 1 fire significant watershed damage has occurred in the Harris Springs Watershed. The proposed project would address erosion form monsoonal events in the upper Harris Springs Canyon Watershed.

Location

The Harris Springs Canyon Watershed (USGS-delineated HUC 6 watershed) is approximately 31,141 acres on the east side of the Spring Mountains range south of Highway 157 (Kyle Canyon Road).

Project timeline

1
Scoping Start
10/15/2018
2
Decision
03/2019 (Estimated)
3
Implementation
04/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Restoration and Soil Erosion Control for Harris Springs AreaDecision Signed Date: 03/28/2019
ForestsHumboldt-Toiyabe National Forest
DistrictsSpring Mountains National Recreation Area
Legal Land DescriptionNot Applicable
Watershed management